8514-8516 W HILLROSE ST 91040

Certificate Information: 8514-8516 W HILLROSE ST 91040

Application / Permit
21014-20000-03174
Plan Check / Job No.
B21VN07982
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ATTACHED (20'-0"x50'-0"), 950 SQFT ATTACHED ADU W/ 15'-0"x14'-0" ( 210 SQFT BREEZEWAY) AND NEW ATTACHED 2 CAR GARAGE ADDITION (20'-0"x18'-0"),360 SQFT TO EXISTING SINGLE FAMILY DWELLING PER LAMC 12.22 A.33(c)(e) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
Issued on 6/27/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/19/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 PETER MOSESIAN
Corrections Issued 8/21/2021 PETER MOSESIAN
Quality Review Completed 8/23/2021 OMID HEDAYAT
Building Plans Picked Up 8/26/2021 APPLICANT
Plan Check Approved 6/27/2022 PETER MOSESIAN
Issued 6/27/2022 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 2/7/2022 MIGUEL GAMBOA
Address approval Cleared 6/27/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/27/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/27/2022 CARLOS AGUILERA
Sewer availability Cleared 6/27/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2022 Approved GREGG CUMMINGS
Pre-Inspection 12/12/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/26/2024 Approved CRAIG DAVIS
PLUMBING-Rough 5/7/2024 Partial Approval WILLIAM WREN
Wood Frame 5/7/2024 Partial Approval WILLIAM WREN
Insulation 5/14/2024 Not Ready for Inspection WILLIAM WREN
Wood Frame 5/14/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/5/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 8/5/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 8/5/2024 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 8/5/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 8/22/2024 Not Ready for Inspection WILLIAM WREN
HVAC-Rough 8/22/2024 Not Ready for Inspection WILLIAM WREN
Wood Frame 8/22/2024 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 8/26/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 8/26/2024 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Rough 8/27/2024 Partial Approval MATTHEW NELSON
Green Building Rough 8/27/2024 Approved MATTHEW NELSON
HVAC-Rough 8/27/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/6/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 9/6/2024 Approved WILLIAM WREN
Insulation 9/18/2024 Approved JACK KARGODORIAN
Drywall Nailing 9/23/2024 Approved WILLIAM WREN
Shower Pan 10/1/2024 Approved WILLIAM WREN
Underground Mechanical 11/4/2024 Partial Approval VINCENT HANLEY
Underground Mechanical 11/18/2024 Approved WILLIAM WREN
Wood Frame 12/12/2025 Not Ready for Inspection DAVID ANDERSON
Final 3/27/2026 Corrections Issued DAVID ANDERSON
Green Building Final 3/27/2026 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 3/27/2026 Approved DAVID ANDERSON
Final 4/23/2026 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 4/23/2026 Approved NICHOLAS TROWBRIDGE
Service/Power Release 4/23/2026 Not Ready for Inspection NICHOLAS TROWBRIDGE