15423 W LA MAIDA ST 91403

Certificate Information: 15423 W LA MAIDA ST 91403

Application / Permit
21014-20000-03144
Plan Check / Job No.
B21VN07900
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ECPC: ADDITION OF A 903 SQ. FT. ACCESSORY DWELLING UNIT TO THE (E) GARAGE. PER LAMC 12.22 A.33 (c) and (d). ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 6/29/2021 LUISANGEL VALENZUELA
Corrections Issued 6/29/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 6/30/2021 APPLICANT
Plan Check Approved 11/2/2022 MOHAMMAD ESMAILI
Issued 2/21/2023 APPLICANT
CofO in Progress 6/7/2024 THOMAS FINNILA
Permit Finaled 8/5/2024 JOHN JANSON
CofO Issued 8/5/2024 JOHN JANSON
Permit Finaled 8/5/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/12/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/13/2021 GABRIEL ROBLES
Sewer availability Cleared 8/13/2021 GABRIEL ROBLES
Low Impact Development Cleared 10/28/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/1/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 3/31/2023 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 3/31/2023 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 4/10/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/10/2023 Approved VINCENT HANLEY
Grounding or Bonding 4/10/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Approved VINCENT HANLEY
Sewer 6/26/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/3/2023 Partial Approval VINCENT HANLEY
Green Building Rough 8/3/2023 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 8/3/2023 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 8/3/2023 Approved VINCENT HANLEY
Underground Mechanical 8/3/2023 Approved VINCENT HANLEY
Wood Frame 8/3/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/21/2023 Approved JEFFREY PARD
HVAC-Rough 9/5/2023 Approved VINCENT HANLEY
Insulation 9/5/2023 Approved VINCENT HANLEY
Drywall Nailing 9/27/2023 Approved VINCENT HANLEY
Green Building Rough 9/27/2023 Approved VINCENT HANLEY
Shower Pan 9/27/2023 Approved VINCENT HANLEY
Service/Power Release 12/1/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 4/12/2024 Approved VINCENT HANLEY
Final 4/12/2024 Corrections Issued VINCENT HANLEY
Green Building Final 4/12/2024 Approved VINCENT HANLEY
MERV13>=Final 4/12/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 4/12/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 5/6/2024 Approved VINCENT HANLEY
Final 5/6/2024 Corrections Issued VINCENT HANLEY
HVAC-Final 5/6/2024 Approved VINCENT HANLEY
PLUMBING-Final 5/6/2024 Approved VINCENT HANLEY
Final 6/3/2024 Corrections Issued THOMAS FINNILA
Final 6/6/2024 OK to Issue CofO THOMAS FINNILA