12201 N MCLENNAN AVE 91344
Certificate Information: 12201 N MCLENNAN AVE 91344
- Application / Permit
- 21014-20000-03127
- Plan Check / Job No.
- B21VN07865
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (16'-1"x 22'-0"), 704 SQFT TWO STORY GROUND FLOOR ADDITION AND INTERIOR REMODEL TO (E) SFD
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | PETER MOSESIAN |
| Corrections Issued | 7/25/2021 | PETER MOSESIAN |
| Quality Review Completed | 8/6/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/10/2021 | APPLICANT |
| Plan Check Approved | 3/3/2022 | PETER MOSESIAN |
| Issued | 3/16/2022 | APPLICANT |
| CofO in Progress | 9/6/2022 | JAVIER RAMOS JR |
| CofO in Progress | 9/8/2022 | ROBERT GOLD |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/14/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/14/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/14/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/14/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 8/14/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 8/18/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 8/18/2021 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 8/19/2021 | MANUEL TEJADA |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/20/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/24/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 11/5/2021 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 2/22/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 4/5/2022 | Partial Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 4/7/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/1/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 6/1/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 6/1/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/7/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 6/7/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 6/7/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/14/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/14/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/14/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/22/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/22/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/24/2022 | Approved | JAVIER RAMOS JR |
| Final | 8/24/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 8/24/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/24/2022 | Approved | JAVIER RAMOS JR |
| Final | 8/29/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 8/29/2022 | Approved | JAVIER RAMOS JR |