5920 N KENTLAND AVE 91367
Certificate Information: 5920 N KENTLAND AVE 91367
- Application / Permit
- 21014-20000-03119
- Plan Check / Job No.
- B21VN07847
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 191 SF ADDITION AND INTERIOR REMODEL TO (E) SFD
- Permit Issued
- Issued on 9/3/2021
- Issuing Office
- Current Status
- CofO Issued on 2/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Application Withdrawn-Void | 6/23/2021 | ALDO UBAU |
| Submitted | 6/23/2021 | APPLICANT |
| Re-Activate Application | 6/23/2021 | ALDO UBAU |
| Assigned to Plan Check Engineer | 6/25/2021 | JESSE ARELLANO |
| Corrections Issued | 6/26/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 7/28/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 8/23/2021 | JESSE ARELLANO |
| Issued | 9/3/2021 | APPLICANT |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| CofO in Progress | 2/2/2022 | TROY SANDERS |
| CofO Issued | 2/9/2022 | JOHN JANSON |
| Permit Finaled | 2/9/2022 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/6/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/6/2021 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 7/9/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2021 | LEE GUILBEAUX |
| Green Code | Cleared | 8/23/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Advanced General Construction; Lic. No.: 951083-B | 6545 HAZELTINE AVE # 212 VAN NUYS, CA 91401 |
| Engineer | Taroian,, Armen; Lic. No.: C78011 | 411 PALM DR APT 204 GLENDALE, CA 91206 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2021 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 9/20/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/13/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 10/19/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 10/19/2021 | Partial Approval | TROY SANDERS |
| Green Building Rough | 10/19/2021 | Not Ready for Inspection | TROY SANDERS |
| MERV13>=Rough | 10/19/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 10/19/2021 | Partial Approval | TROY SANDERS |
| Shower Pan | 10/19/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 10/26/2021 | Approved | TROY SANDERS |
| Deputy Wood Construction | 10/26/2021 | Approved | TROY SANDERS |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | TROY SANDERS |
| MERV13>=Rough | 10/26/2021 | Approved | TROY SANDERS |
| Insulation | 11/1/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/1/2021 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 11/5/2021 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/25/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 1/25/2022 | Approved | DAVID SCANTLIN |
| Final | 1/25/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 1/25/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 1/25/2022 | Approved | DAVID SCANTLIN |
| HVAC-Final | 1/25/2022 | Approved | DAVID SCANTLIN |
| MERV13>=Final | 1/25/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 1/25/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 1/25/2022 | Approved | DAVID SCANTLIN |
| Final | 2/1/2022 | OK to Issue CofO | TROY SANDERS |