23711 W CLARENDON ST 91367
Certificate Information: 23711 W CLARENDON ST 91367
- Application / Permit
- 21014-20000-03115
- Plan Check / Job No.
- B21VN07831
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 18'-9" X 20'-10" ADDITION OF A BEDROOM, BATHROOM AND CLOSET TO (E) SFD.
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 6/26/2021 | ARTIN ZARUKIAN |
| No Progress | 1/27/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 2/15/2022 | ARTIN ZARUKIAN |
| Issued | 2/15/2022 | APPLICANT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| CofO in Progress | 6/13/2022 | TROY SANDERS |
| Permit Finaled | 6/15/2022 | JOHN JANSON |
| CofO Issued | 6/15/2022 | JOHN JANSON |
| Permit Finaled | 6/15/2022 | JOHN JANSON |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 7/26/2021 | TIMOTHY POWELL |
| Roof/Waste drainage to street | Cleared | 7/28/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Progressive Builders Inc; Lic. No.: 1009285-B | 7445 TPNG CYN BLVD STE 220 CANOGA PARK, CA 91303 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/11/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 3/16/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 3/31/2022 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 4/12/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 4/12/2022 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 4/12/2022 | Approved | PETER FOLLING |
| Shower Pan | 4/12/2022 | Approved | PETER FOLLING |
| Insulation | 4/15/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/15/2022 | Approved | MORRIS JACKSON |
| HVAC-Rough | 4/19/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 4/21/2022 | Approved | TROY SANDERS |
| Green Building Rough | 4/21/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 6/10/2022 | Approved | TROY SANDERS |
| Final | 6/10/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 6/10/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 6/10/2022 | Approved | TROY SANDERS |