10601 N HELENDALE AVE 91042

Certificate Information: 10601 N HELENDALE AVE 91042

Application / Permit
21014-20000-03099
Plan Check / Job No.
B21VN07780
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERT EXISTING GARAGE TO ADU & ADDITIONS TO FRONT AND REAR
Permit Issued
Issued on 1/6/2023
Issuing Office
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 JOE VO
Corrections Issued 7/24/2021 JOE VO
Quality Review Completed 7/27/2021 MICHAEL PEREZ
Plan Check Approved 9/22/2022 JOE VO
Issued 1/6/2023 APPLICANT
CofO in Progress 2/14/2024 WILLIAM WREN
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/22/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/10/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 7/8/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 7/11/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 7/14/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 12/6/2022 JOE VO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/8/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 5/12/2023 Corrections Issued WILLIAM WREN
PLUMBING-Rough 5/12/2023 Partial Approval WILLIAM WREN
Footing/Foundation/Slab 5/22/2023 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 6/6/2023 Corrections Issued WILLIAM WREN
Deputy Reinf. Concrete 6/8/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 6/12/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 7/20/2023 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Approved WILLIAM WREN
PLUMBING-Rough 8/30/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 9/8/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 9/8/2023 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 9/20/2023 Approved WILLIAM WREN
HVAC-Rough 9/20/2023 Approved WILLIAM WREN
Insulation 9/20/2023 Approved WILLIAM WREN
Drywall Nailing 9/25/2023 Approved WILLIAM WREN
Shower Pan 10/2/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 10/13/2023 Approved DAVID ANDERSON
PLUMBING-Final 10/13/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Final 10/20/2023 Partial Inspection WILLIAM WREN
PLUMBING-Rough 11/28/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 12/4/2023 Approved WILLIAM WREN
Final 12/22/2023 Corrections Issued WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Approved WILLIAM WREN
Smoke Detectors 12/22/2023 Approved WILLIAM WREN
Final 1/2/2024 Not Ready for Inspection MATTHEW NELSON
Final 1/9/2024 OK to Issue CofO WILLIAM WREN