10601 N HELENDALE AVE 91042
Certificate Information: 10601 N HELENDALE AVE 91042
- Application / Permit
- 21014-20000-03099
- Plan Check / Job No.
- B21VN07780
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERT EXISTING GARAGE TO ADU & ADDITIONS TO FRONT AND REAR
- Permit Issued
- Issued on 1/6/2023
- Issuing Office
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | JOE VO |
| Corrections Issued | 7/24/2021 | JOE VO |
| Quality Review Completed | 7/27/2021 | MICHAEL PEREZ |
| Plan Check Approved | 9/22/2022 | JOE VO |
| Issued | 1/6/2023 | APPLICANT |
| CofO in Progress | 2/14/2024 | WILLIAM WREN |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 7/8/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/14/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 12/6/2022 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/8/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 5/12/2023 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 5/12/2023 | Partial Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 5/22/2023 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/6/2023 | Corrections Issued | WILLIAM WREN |
| Deputy Reinf. Concrete | 6/8/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 6/12/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/20/2023 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 8/30/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/8/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/8/2023 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 9/20/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 9/20/2023 | Approved | WILLIAM WREN |
| Insulation | 9/20/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/25/2023 | Approved | WILLIAM WREN |
| Shower Pan | 10/2/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/13/2023 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 10/13/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Final | 10/20/2023 | Partial Inspection | WILLIAM WREN |
| PLUMBING-Rough | 11/28/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 12/4/2023 | Approved | WILLIAM WREN |
| Final | 12/22/2023 | Corrections Issued | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Approved | WILLIAM WREN |
| Smoke Detectors | 12/22/2023 | Approved | WILLIAM WREN |
| Final | 1/2/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 1/9/2024 | OK to Issue CofO | WILLIAM WREN |