4704 N BALBOA AVE 91316

Certificate Information: 4704 N BALBOA AVE 91316

Application / Permit
21014-20000-03089
Plan Check / Job No.
B21VN07748
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 12' X 15'-6" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/13/2022
Issuing Office
Current Status
CofO Issued on 1/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 6/18/2021 RAPHAEL ROSAS
Corrections Issued 6/19/2021 RAPHAEL ROSAS
Applicant returned to address corrections 7/19/2021 RAPHAEL ROSAS
Plan Check Approved 1/31/2022 RAPHAEL ROSAS
Building Plans Picked Up 2/3/2022 APPLICANT
Issued 2/13/2022 APPLICANT
CofO in Progress 1/12/2023 VINCENT HANLEY
Permit Finaled 1/31/2023 JOHN JANSON
CofO Issued 1/31/2023 JOHN JANSON
Permit Finaled 1/31/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/30/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/30/2021 GABRIEL ROBLES
Sewer availability Cleared 9/30/2021 GABRIEL ROBLES
ZA Case Cleared 9/30/2021 LAUREN PADICK
ZA Case Cleared 9/30/2021 LAUREN PADICK
Grading Pre-Inspection Cleared 11/3/2021 TIMOTHY POWELL
Hydrant and Access approval Cleared 12/21/2021 MATTHEW CRAIG
Construction near power lines Cleared 12/30/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: C84559 9163 LEROY STREET      SAN GABRIEL, CA 91775

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/5/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 4/15/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 4/15/2022 Corrections Issued DAVID SANDOVAL
Underground Mechanical 4/19/2022 Partial Approval DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 4/21/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 4/21/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 6/27/2022 Corrections Issued VINCENT HANLEY
Green Building Rough 6/27/2022 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 6/27/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/27/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 6/27/2022 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 7/1/2022 Approved VINCENT HANLEY
Wood Frame 7/1/2022 Partial Approval VINCENT HANLEY
Insulation 7/6/2022 Not Ready for Inspection MORRIS JACKSON
Insulation 7/8/2022 Approved MICHAEL SMITH
Drywall Nailing 7/13/2022 Approved VINCENT HANLEY
Insulation 7/13/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/5/2022 Approved VINCENT HANLEY
Shower Pan 8/5/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/9/2022 Partial Inspection MORRIS JACKSON
BUILDING-Rough-Frame 9/13/2022 Approved VINCENT HANLEY
Final 9/13/2022 Corrections Issued VINCENT HANLEY
Green Building Final 9/13/2022 Approved VINCENT HANLEY
Green Building Rough 9/13/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/13/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 9/13/2022 Approved VINCENT HANLEY
Final 10/17/2022 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 1/11/2023 Approved VINCENT HANLEY
Final 1/11/2023 OK to Issue CofO VINCENT HANLEY
HVAC-Final 1/11/2023 Approved VINCENT HANLEY