20596 W STRATHERN ST 91306
Certificate Information: 20596 W STRATHERN ST 91306
- Application / Permit
- 21014-20000-03082
- Plan Check / Job No.
- B21VN07741
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 366 SQ FT. GARAGE TO ACCESSORY DWELLING UNIT WITH 42'X22', 833 SQ. FT. ADDITION PER LAMC 12.22A33(C)&(D). ALL WORK PER ENGINEERING. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | COLIN LOREDO |
| Corrections Issued | 8/10/2021 | COLIN LOREDO |
| Quality Review Completed | 8/18/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 8/30/2021 | APPLICANT |
| Plan Check Approved | 9/28/2021 | COLIN LOREDO |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | ALEXANDER HANDY |
| Permit Finaled | 1/6/2023 | JOHN JANSON |
| CofO Issued | 1/6/2023 | JOHN JANSON |
| Permit Finaled | 1/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 9/23/2021 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 9/23/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Flip It Homes Inc; Lic. No.: 1043456-B | 20501 VENTURA BLVD #135 WOODLAND HILLS, CA 91364 |
| Engineer | Sadjadi,, Abdulreza; Lic. No.: C51812 | 1223 WILSHIRE BLVD #169 SANTA MONICA, CA 90403 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/10/2022 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 3/16/2022 | Conditional Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 3/16/2022 | Corrections Issued | STEVEN BACK |
| Deputy Wood Construction | 4/5/2022 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/3/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Partial Approval | STEVEN BACK |
| Green Building Rough | 5/3/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 5/3/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/3/2022 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 5/16/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/16/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/18/2022 | Approved | STEVEN BACK |
| Green Building Rough | 5/18/2022 | Approved | STEVEN BACK |
| Insulation | 5/24/2022 | Conditional Approval | JESUS PINEDA |
| Drywall Nailing | 6/7/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/7/2022 | Approved | JESUS PINEDA |
| Shower Pan | 6/7/2022 | Approved | JESUS PINEDA |
| Sewer | 8/1/2022 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 12/22/2022 | Approved | ALEXANDER HANDY |
| Final | 12/22/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/22/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 12/22/2022 | Approved | ALEXANDER HANDY |
| HVAC-Final | 12/22/2022 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Final | 12/22/2022 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 12/22/2022 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 12/27/2022 | Approved | ALEXANDER HANDY |
| Final | 12/27/2022 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 12/27/2022 | Approved | ALEXANDER HANDY |
| Final | 1/3/2023 | OK to Issue CofO | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/3/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Approved | ALEXANDER HANDY |