1116 E NOWITA PL 90291
Certificate Information: 1116 E NOWITA PL 90291
- Application / Permit
- 21014-20000-03080
- Plan Check / Job No.
- B21VN07739
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 9'-9" x 18'2" ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | SELLA BENYAMIN |
| Corrections Issued | 7/29/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/30/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Plan Check Approved | 8/31/2021 | SELLA BENYAMIN |
| Issued | 10/12/2021 | APPLICANT |
| CofO in Progress | 3/2/2023 | EVAN COOPER |
| Permit Finaled | 3/9/2023 | DANIEL ORRANTE |
| CofO Issued | 3/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/17/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 8/17/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Clark Kitchen Cabinets; Lic. No.: 645164-B | 854 AMOROSO PLACE VENICE, CA 90291 |
| Engineer | Ashley,, William Mark; Lic. No.: C34299 | 5170 FINLANDIA WAY CARMICHAEL, CA 95608 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/20/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Partial Approval | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 11/23/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 11/23/2021 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 12/17/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 12/17/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/17/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 12/22/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 1/14/2022 | Corrections Issued | DAVID FEILER |
| Wood Frame | 1/14/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 4/28/2022 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 5/19/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/19/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/19/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 5/19/2022 | Conditional Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/19/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Deputy Wood Construction | 5/20/2022 | Conditional Approval | RICHARD STEINBACH |
| Interior/Exterior Lathing | 6/1/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/28/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 8/2/2022 | Approved | STEPHANIE SWANSON |
| Insulation | 8/2/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/2/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/10/2022 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 10/31/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 11/1/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 11/9/2022 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 11/9/2022 | Not Ready for Inspection | DAVID FEILER |
| Special/Order Compliance | 11/9/2022 | Partial Inspection | CLAYTON GRAHAM |
| Green Building Rough | 11/14/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/14/2022 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 2/7/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 2/7/2023 | Approved | EVAN COOPER |
| Final | 2/7/2023 | Corrections Issued | EVAN COOPER |
| Gas Test | 2/7/2023 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 2/7/2023 | Approved | EVAN COOPER |
| HVAC-Final | 2/7/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/7/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 2/7/2023 | Approved | EVAN COOPER |
| Final | 2/21/2023 | Corrections Issued | EVAN COOPER |
| Final | 3/1/2023 | OK to Issue CofO | EVAN COOPER |