6513 N YARMOUTH AVE 91335

Certificate Information: 6513 N YARMOUTH AVE 91335

Application / Permit
21014-20000-03071
Plan Check / Job No.
B21VN07724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Addition to and conversion of the existing garage to a new Accessory Dwelling Unit per ordinance.
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 3/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/2/2021 MICHAEL LOPEZ
Corrections Issued 7/2/2021 MICHAEL LOPEZ
Plan Check Approved 7/29/2021 MICHAEL LOPEZ
Issued 8/3/2021 APPLICANT
CofO in Progress 2/22/2022 VINCENT HANLEY
CofO Issued 3/6/2022 MICHAEL SMITH
Permit Finaled 3/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/12/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/12/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/12/2021 CARLOS AGUILERA
Sewer availability Cleared 7/12/2021 CARLOS AGUILERA
Construction near power lines Cleared 7/13/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/12/2021 Approved RONALD COWAN
Underground Mechanical 8/12/2021 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 8/17/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/5/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 10/5/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Approved VINCENT HANLEY
HVAC-Rough 10/5/2021 Approved VINCENT HANLEY
PLUMBING-Rough 10/5/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/8/2021 Approved VINCENT HANLEY
Green Building Rough 10/8/2021 Approved VINCENT HANLEY
Insulation 10/8/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/8/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/29/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Approved VINCENT HANLEY
Green Building Rough 10/29/2021 Approved VINCENT HANLEY
Insulation 10/29/2021 Approved VINCENT HANLEY
Underground Mechanical 10/29/2021 Partial Approval VINCENT HANLEY
Drywall Nailing 11/5/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/5/2021 Approved VINCENT HANLEY
Shower Pan 11/5/2021 Approved VINCENT HANLEY
Underground Mechanical 11/10/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 12/22/2021 Approved VINCENT HANLEY
Final 12/22/2021 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 12/22/2021 Approved VINCENT HANLEY
HVAC-Final 12/22/2021 Corrections Issued VINCENT HANLEY
PLUMBING-Final 12/22/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 12/22/2021 Approved VINCENT HANLEY
Smoke Detectors 12/22/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 2/18/2022 Approved VINCENT HANLEY
Final 2/18/2022 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/18/2022 Approved VINCENT HANLEY
PLUMBING-Final 2/18/2022 Approved VINCENT HANLEY