3818 N GLENEAGLES DR 91356

Certificate Information: 3818 N GLENEAGLES DR 91356

Application / Permit
21014-20000-03055
Plan Check / Job No.
B21VN07710
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
454 SF ADDITION WITH COVERED PATIO TO THE (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 1/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 COLIN LOREDO
Corrections Issued 8/5/2021 COLIN LOREDO
Quality Review Completed 8/18/2021 OMID HEDAYAT
Building Plans Picked Up 8/20/2021 APPLICANT
Plan Check Approved 3/3/2022 COLIN LOREDO
Issued 3/10/2022 APPLICANT
CofO in Progress 1/17/2024 SEAN HAUPT
Permit Finaled 1/26/2024 JOHN JANSON
CofO Issued 1/26/2024 JOHN JANSON
Permit Finaled 1/26/2024 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/29/2021 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 10/1/2021 CARLOS AGUILERA
Specific Plan Cleared 10/26/2021 OLGA AYALA
ZA Case Cleared 10/26/2021 OLGA AYALA
ZA Case Cleared 10/26/2021 OLGA AYALA
Low Impact Development Cleared 2/1/2022 TA ANH
Roof/Waste drainage to street Cleared 2/3/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/21/2022 Corrections Issued DAVID SANDOVAL
Underground Mechanical 6/21/2022 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 6/27/2022 Approved DAVID SANDOVAL
Deputy Steel/Welding 8/1/2022 Conditional Approval DAVID SANDOVAL
Deputy Steel/Welding 9/6/2022 Conditional Approval DAVID SANDOVAL
HVAC-Rough 10/5/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 10/5/2022 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 10/24/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 10/24/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 10/24/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 10/24/2022 Approved DAVID SANDOVAL
Structural Steel Frame 10/24/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 3/1/2023 Partial Approval DAVID SANDOVAL
Special/Order Compliance 3/1/2023 Partial Inspection JUSTIN HAWLEY
Insulation 3/2/2023 Approved DAVID SANDOVAL
Drywall Nailing 3/14/2023 Approved DAVID SANDOVAL
Green Building Rough 3/14/2023 Approved DAVID SANDOVAL
Shower Pan 3/14/2023 Approved DAVID SANDOVAL
Underground Mechanical 7/26/2023 Approved SEAN HAUPT
ELECTRICAL-Final 11/9/2023 Approved SEAN HAUPT
Final 11/9/2023 Corrections Issued SEAN HAUPT
HVAC-Final 11/9/2023 Approved SEAN HAUPT
PLUMBING-Final 11/9/2023 Approved SEAN HAUPT
Final 12/4/2023 Corrections Issued JOHN KIDWELL
Green Building Final 12/4/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 12/4/2023 Approved JOHN KIDWELL
Final 1/16/2024 OK to Issue CofO SEAN HAUPT
Green Building Final 1/16/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Approved SEAN HAUPT