15540 W WOODCREST DR 91403

Certificate Information: 15540 W WOODCREST DR 91403

Application / Permit
21014-20000-03043
Plan Check / Job No.
B21VN07664
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE FOR (2) NEW BEDROOMS AND ADD 19'-4" X 19'-3" ATTACHED CARPORT. REMODEL (E) BEDROOM FOR HALLWAY AND BATHROOM. WORK PER ENGINEER.
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 12/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 6/18/2021 ROSENDO MEDINA
Corrections Issued 6/19/2021 ROSENDO MEDINA
Applicant returned to address corrections 7/17/2021 ROSENDO MEDINA
Plan Check Approved 7/29/2021 ROSENDO MEDINA
Building Plans Picked Up 7/30/2021 APPLICANT
Issued 9/7/2021 APPLICANT
CofO in Progress 12/10/2021 ROBERT GOLD
CofO Issued 12/10/2021 MICHAEL SMITH
Permit Finaled 12/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/9/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/9/2021 CARLOS AGUILERA
Sewer availability Cleared 7/9/2021 CARLOS AGUILERA
ZA Case Cleared 7/9/2021 MARITZA PRZEKOP
Grading Pre-Inspection Cleared 7/16/2021 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,
Engineer Asprer,, Anjero; Lic. No.: C91126 10480 SUNLAND BLVD 53      SUNLAND, CA 91040

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/14/2021 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 9/23/2021 Corrections Issued RONALD COWAN
Green Building Rough 9/23/2021 Corrections Issued RONALD COWAN
MERV13>=Rough 9/23/2021 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 9/28/2021 Approved RONALD COWAN
PLUMBING-Rough 9/28/2021 Approved RONALD COWAN
Pre-Inspection 9/28/2021 Corrections Issued RONALD COWAN
Insulation 9/29/2021 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 9/29/2021 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 9/30/2021 Partial Approval RONALD COWAN
Green Building Rough 9/30/2021 Approved RONALD COWAN
MERV13>=Rough 9/30/2021 Approved RONALD COWAN
Insulation 10/1/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 10/1/2021 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 10/7/2021 Approved RONALD COWAN
Drywall Nailing 10/7/2021 Approved RONALD COWAN
Interior/Exterior Lathing 10/7/2021 Approved RONALD COWAN
Final 10/26/2021 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 10/26/2021 Approved PETER FOLLING
Green Building Final 10/26/2021 Approved PETER FOLLING
MERV13>=Final 10/26/2021 Not Ready for Inspection PETER FOLLING
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Not Ready PETER FOLLING
Smoke Detectors 10/26/2021 Approved PETER FOLLING
Final 10/28/2021 Not Ready for Inspection PETER FOLLING
Final 12/10/2021 OK to Issue CofO ROBERT GOLD
MERV13>=Final 12/10/2021 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved ROBERT GOLD