459 S SHERBOURNE DR 90048
Certificate Information: 459 S SHERBOURNE DR 90048
- Application / Permit
- 21014-20000-03040
- Plan Check / Job No.
- B21VN07659
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FIRST STORY ADDITION WITH A ROOF DECK TO (E) SFD
- Permit Issued
- Issued on 3/1/2022
- Issuing Office
- Current Status
- CofO Issued on 1/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | MARVEL DELACRUZ |
| Corrections Issued | 7/28/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 7/30/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/3/2021 | APPLICANT |
| Plan Check Approved | 2/14/2022 | MARVEL DELACRUZ |
| Issued | 3/1/2022 | APPLICANT |
| CofO in Progress | 1/16/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 1/17/2024 | DANIEL ORRANTE |
| CofO Issued | 1/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/8/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 12/23/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 12/28/2021 | JEANETTE VONG |
| Green Code | Cleared | 2/12/2022 | MARVEL DELACRUZ |
Contact Information
| Contractor | La Remodeling Co; Lic. No.: 932510-B | 6000 YORK BLVD STE A LOS ANGELES, CA 90042 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/23/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/25/2022 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 3/25/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 3/25/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 5/24/2022 | Approved | EVAN COOPER |
| Underground Mechanical | 6/3/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 6/7/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | EVAN COOPER |
| Green Building Rough | 7/29/2022 | Approved | EVAN COOPER |
| METHANE-Rough | 7/29/2022 | Approved | EVAN COOPER |
| Rough-Elec/Plmb/HVAC | 7/29/2022 | Corrections Issued | EVAN COOPER |
| Insulation | 8/3/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/3/2022 | Approved | EVAN COOPER |
| Shower Pan | 8/3/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 8/8/2022 | Approved | EVAN COOPER |
| Final | 10/13/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 10/13/2023 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 10/13/2023 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 10/13/2023 | Approved | MEL KHACHATOURIAN |
| Final | 1/17/2024 | OK to Issue CofO | MEL KHACHATOURIAN |