459 S SHERBOURNE DR 90048

Certificate Information: 459 S SHERBOURNE DR 90048

Application / Permit
21014-20000-03040
Plan Check / Job No.
B21VN07659
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRST STORY ADDITION WITH A ROOF DECK TO (E) SFD
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 MARVEL DELACRUZ
Corrections Issued 7/28/2021 MARVEL DELACRUZ
Quality Review Completed 7/30/2021 STEVEN KIM
Building Plans Picked Up 8/3/2021 APPLICANT
Plan Check Approved 2/14/2022 MARVEL DELACRUZ
Issued 3/1/2022 APPLICANT
CofO in Progress 1/16/2024 MEL KHACHATOURIAN
Permit Finaled 1/17/2024 DANIEL ORRANTE
CofO Issued 1/17/2024 DANIEL ORRANTE
Permit Finaled 1/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/4/2021 CECILIO NAVARRO
Sewer availability Cleared 9/8/2021 CECILIO NAVARRO
Low Impact Development Cleared 12/23/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 12/28/2021 JEANETTE VONG
Green Code Cleared 2/12/2022 MARVEL DELACRUZ

Contact Information

Contractor La Remodeling Co; Lic. No.: 932510-B 6000 YORK BLVD STE A      LOS ANGELES, CA 90042
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/23/2022 Approved MICHAEL PELHAM
Footing/Foundation/Slab 3/25/2022 Corrections Issued EVAN COOPER
METHANE-Barrier 3/25/2022 Approved EVAN COOPER
METHANE-Subgrade 3/25/2022 Approved EVAN COOPER
Footing/Foundation/Slab 5/24/2022 Approved EVAN COOPER
Underground Mechanical 6/3/2022 Partial Approval OGANES TARAKHCHYAN
Insulation 6/7/2022 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 7/29/2022 Approved EVAN COOPER
Green Building Rough 7/29/2022 Approved EVAN COOPER
METHANE-Rough 7/29/2022 Approved EVAN COOPER
Rough-Elec/Plmb/HVAC 7/29/2022 Corrections Issued EVAN COOPER
Insulation 8/3/2022 Approved EVAN COOPER
Interior/Exterior Lathing 8/3/2022 Approved EVAN COOPER
Shower Pan 8/3/2022 Approved EVAN COOPER
Drywall Nailing 8/8/2022 Approved EVAN COOPER
Final 10/13/2023 Corrections Issued MEL KHACHATOURIAN
Green Building Final 10/13/2023 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved MEL KHACHATOURIAN
Smoke Detectors 10/13/2023 Approved MEL KHACHATOURIAN
Final 1/17/2024 OK to Issue CofO MEL KHACHATOURIAN