8664-8666 W PICO BLVD 90035
Certificate Information: 8664-8666 W PICO BLVD 90035
- Application / Permit
- 21014-20000-03033
- Plan Check / Job No.
- B21VN07649
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- OFFICE ADDITION AT 1ST & 2ND FLOOR
- Permit Issued
- Issued on 8/3/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/3/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | SELLA BENYAMIN |
| Corrections Issued | 7/29/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/30/2021 | STEVEN KIM |
| Building Plans Picked Up | 8/5/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 8/5/2021 | APPLICANT |
| Green Plans Picked Up | 8/5/2021 | APPLICANT |
| Applicant returned to address corrections | 6/23/2022 | SELLA BENYAMIN |
| Plan Check Approved | 6/29/2022 | SELLA BENYAMIN |
| Issued | 8/3/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/8/2022 | JEANIE LAM |
| ZA Case | Cleared | 2/8/2022 | DANG NGUYEN |
| ZA Case | Cleared | 2/8/2022 | DANG NGUYEN |
| ZA Case | Cleared | 2/8/2022 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2022 | JEANIE LAM |
| Sewer availability | Cleared | 2/9/2022 | JEANIE LAM |
| Green Code | Cleared | 3/24/2022 | MICHAEL AYERS |
| DAS Clearance | Cleared | 6/2/2022 | OLLIE CARTER |
Contact Information
| Architect | Mohabir,, Edwin Ramkishore; Lic. No.: C23674 | 25206 BISHOP CT. VALENCIA, CA 91381 |
| Contractor | J&S Realty And Development Inc; Lic. No.: 515647-B | 410 CLOVERLEAF DRIVE BALDWIN PARK, CA 91706 |
| Engineer | Lota,, Dante S; Lic. No.: S2314 | 19325 TRENTHAM AVE CERRITOS, CA 90701 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 8/25/2022 | Conditional Approval | TED RIES |
| Excavation/Setback/Form/Re-Bar | 9/1/2022 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 9/29/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Barrier | 9/29/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Subgrade | 9/29/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Not Ready for Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 10/5/2022 | Not Ready for Inspection | NICK LAROCCA |
| METHANE-Barrier | 10/5/2022 | Not Ready for Inspection | NICK LAROCCA |
| METHANE-Subgrade | 10/5/2022 | Not Ready for Inspection | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 10/12/2022 | Partial Approval | JEFF BYTHEWAY |
| Masonry Wall/Backfill | 10/27/2022 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 11/21/2022 | Approved | FARHAD DADBIN |
| Green Building Rough | 11/28/2022 | Not Ready for Inspection | NICK LAROCCA |
| METHANE-Rough | 11/28/2022 | Not Ready for Inspection | NICK LAROCCA |
| Wood Frame | 11/28/2022 | Not Ready for Inspection | NICK LAROCCA |
| Green Building Rough | 12/1/2022 | Not Ready for Inspection | GRANT WOODS |
| METHANE-Rough | 12/1/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 12/1/2022 | Partial Approval | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Corrections Issued | FARHAD DADBIN |
| Deputy Wood Construction | 12/19/2022 | Corrections Issued | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Corrections Issued | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 2/3/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Interior/Exterior Lathing | 2/10/2023 | Partial Approval | FARHAD DADBIN |
| Insulation | 2/22/2023 | Corrections Issued | FARHAD DADBIN |
| Pre-Inspection | 2/24/2023 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 2/24/2023 | Partial Inspection | SORIN CIRSTOIU |
| Insulation | 3/6/2023 | Partial Inspection | FARHAD DADBIN |
| Drywall Nailing | 3/9/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Drywall Nailing | 3/23/2023 | Conditional Approval | FARHAD DADBIN |
| Final | 6/27/2023 | Conditional Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 6/27/2023 | Approved | FARHAD DADBIN |
| Green Building Final | 6/27/2023 | Approved | FARHAD DADBIN |
| Green Building Rough | 6/27/2023 | Approved | FARHAD DADBIN |
| METHANE-Barrier | 6/27/2023 | Approved | FARHAD DADBIN |
| METHANE-Final | 6/27/2023 | Approved | FARHAD DADBIN |
| METHANE-Rough | 6/27/2023 | Approved | FARHAD DADBIN |
| METHANE-Subgrade | 6/27/2023 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 6/27/2023 | Approved | FARHAD DADBIN |
| Wood Frame | 6/27/2023 | Approved | FARHAD DADBIN |