6223 S 4TH AVE 90043
Certificate Information: 6223 S 4TH AVE 90043
- Application / Permit
- 21014-20000-03028
- Plan Check / Job No.
- B21VN07622
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 8'-10" x 14'-10" to existing single-family dwelling to add full bathroom. Remodel kitchen and existing bedroom. Remove portion of non-bearing wall between kitchen and living room.
- Permit Issued
- Issued on 9/11/2021
- Issuing Office
- Current Status
- Issued on 9/11/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2021 | ANGELICA DAVE |
| Corrections Issued | 6/22/2021 | ANGELICA DAVE |
| Plan Check Approved | 8/18/2021 | ANGELICA MARTINEZ |
| Building Plans Picked Up | 8/19/2021 | APPLICANT |
| Issued | 9/11/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/21/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Yor Construction And Investments Inc; Lic. No.: 978430-B | 12135 MIRANDA ST VALLEY VILLAGE, CA 91607 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/13/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/25/2021 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 10/25/2021 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 12/23/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/3/2022 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 1/3/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 1/3/2022 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 1/3/2022 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/28/2022 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/28/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/28/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/28/2022 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 2/7/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/7/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/7/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 2/11/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 2/11/2022 | Partial Approval | HORACE FULTZ |