13926 W OTSEGO ST 91423

Certificate Information: 13926 W OTSEGO ST 91423

Application / Permit
21014-20000-03020
Plan Check / Job No.
B21VN07600
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A NEW 15'3" x 10' ATTACHED LATTICE ROOF PATIO COVER TO (E) SFD.
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 7/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 6/16/2021 OMAR GARNICA
Corrections Issued 6/17/2021 OMAR GARNICA
Plan Check Approved 7/20/2021 OMAR GARNICA
Building Plans Picked Up 8/9/2021 APPLICANT
Issued 8/12/2021 APPLICANT
CofO in Progress 6/8/2022 MISAEL ESPARZA
CofO in Progress 6/15/2022 MISAEL ESPARZA
Permit Finaled 7/18/2022 MICHAEL SMITH
CofO Issued 7/18/2022 MICHAEL SMITH
Permit Finaled 7/18/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/23/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/23/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Tuna,, Suleyman; Lic. No.: C73294 3332 BENNETT DRIVE      LOS ANGELES, CA 90068

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/8/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 12/16/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 12/22/2021 Corrections Issued MISAEL ESPARZA
Deputy Reinf. Concrete 1/6/2022 Partial Approval MATT KELLERMAN
Wood Frame 2/25/2022 Corrections Issued MISAEL ESPARZA
Wood Frame 3/7/2022 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 3/11/2022 Approved MISAEL ESPARZA
Drywall Nailing 6/1/2022 Approved MISAEL ESPARZA
Final 6/1/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/1/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/1/2022 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 6/1/2022 Corrections Issued MISAEL ESPARZA
Structural Steel Frame 6/1/2022 Approved MISAEL ESPARZA
Final 6/7/2022 OK to Issue CofO MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 6/7/2022 Approved MISAEL ESPARZA
Final 6/14/2022 OK to Issue CofO MISAEL ESPARZA