19426 W WELBY WAY 91335
Certificate Information: 19426 W WELBY WAY 91335
- Application / Permit
- 21014-20000-03007
- Plan Check / Job No.
- B21VN07573
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 209 SQ. FT. ADDITION OF A BATHROOM AND LAUNDRY ROOM TO THE REAR OF THE (E) SFD. INCLUDE PLUMBING, ELECTRICAL AND MACHANICAL. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 4/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2021 | COLIN LOREDO |
| Corrections Issued | 7/8/2021 | COLIN LOREDO |
| Plan Check Approved | 7/28/2021 | COLIN LOREDO |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Issued | 9/27/2021 | APPLICANT |
| CofO in Progress | 3/30/2022 | WILL MCCONNAUGHY |
| CofO Issued | 4/29/2022 | MICHAEL SMITH |
| Permit Finaled | 4/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/2/2021 | LEE GUILBEAUX |
| ZI | Cleared | 9/3/2021 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Hudnall Construction; Lic. No.: 1036622-B | 18224 GRESHAM ST NORTHRIDGE, CA 91325 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/18/2021 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 11/23/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/26/2022 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 1/26/2022 | Approved | VINCENT HANLEY |
| Insulation | 1/31/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 1/31/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 2/7/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/7/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/7/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/29/2022 | Approved | VINCENT HANLEY |
| Final | 3/29/2022 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 3/29/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 3/29/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/29/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 3/29/2022 | Approved | VINCENT HANLEY |