5017 W ELMWOOD AVE 90004
Certificate Information: 5017 W ELMWOOD AVE 90004
- Application / Permit
- 21014-20000-02997
- Plan Check / Job No.
- B21VN07550
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/26/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/10/2022
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | COLIN LOREDO |
| Corrections Issued | 7/19/2021 | COLIN LOREDO |
| Quality Review Completed | 7/30/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Plan Check Approved | 8/26/2021 | COLIN LOREDO |
| Issued | 8/26/2021 | APPLICANT |
| Permit Finaled | 3/8/2022 | ARTHUR SARGSYAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/13/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
| Engineer | Rosepink,, Dustin Keith; Lic. No.: S5885 | 24255 VIA MADRUGADA MISSION VIEJO, CA 92692 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/4/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 11/8/2021 | Conditional Approval | MASHEL JONGERT |
| ELECTRICAL-Rough | 11/8/2021 | Conditional Approval | MASHEL JONGERT |
| Green Building Rough | 11/8/2021 | Approved | MASHEL JONGERT |
| HVAC-Rough | 11/8/2021 | Approved | MASHEL JONGERT |
| PLUMBING-Rough | 11/8/2021 | Approved | MASHEL JONGERT |
| Deputy Wood Construction | 11/17/2021 | Conditional Approval | MASHEL JONGERT |
| BUILDING-Rough-Frame | 11/19/2021 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/19/2021 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 11/19/2021 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 11/19/2021 | Partial Approval | CRAIG DAVIS |
| Interior/Exterior Lathing | 11/30/2021 | Approved | MASHEL JONGERT |
| Insulation | 12/8/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 12/21/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| Final | 3/8/2022 | Permit Finaled | ARTHUR SARGSYAN |
| Green Building Final | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/8/2022 | Approved | ARTHUR SARGSYAN |