6502 N QUAKERTOWN AVE 91367
Certificate Information: 6502 N QUAKERTOWN AVE 91367
- Application / Permit
- 21014-20000-02996
- Plan Check / Job No.
- B21VN07549
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 8'-0" X 34'-3" ADDITION TO EXPAND (E) KITCHEN, BATHROOM & DINING ROOM AND 33'-2" X 10'-0" PATIO ADDITION TO THE (E) SFD.
- Permit Issued
- Issued on 9/24/2021
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 9/24/2021 | ARTIN ZARUKIAN |
| Issued | 9/24/2021 | APPLICANT |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| CofO in Progress | 7/17/2023 | ALEXANDER HANDY |
| Permit Finaled | 4/15/2025 | JOHN JANSON |
| CofO Issued | 4/15/2025 | JOHN JANSON |
| Permit Finaled | 4/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 9/15/2021 | SAHIL SHARMA |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 6/23/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2022 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 7/1/2022 | Partial Approval | STEVEN BACK |
| Wood Frame | 7/1/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 8/30/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 8/30/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/30/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 9/15/2022 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 9/15/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 9/15/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/20/2022 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 10/20/2022 | Approved | STEVEN BACK |
| Insulation | 10/20/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 10/20/2022 | Approved | STEVEN BACK |
| Shower Pan | 10/20/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 11/17/2022 | No Access for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | No Access for Inspection | STEVEN BACK |
| Insulation | 11/17/2022 | No Access for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 11/28/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Approved | STEVEN BACK |
| Insulation | 11/28/2022 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 12/20/2022 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 6/12/2023 | Corrections Issued | ALEXANDER HANDY |
| Final | 6/12/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 6/12/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 6/12/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 6/12/2023 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Not Ready | ALEXANDER HANDY |
| Service/Power Release | 6/12/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 6/12/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 6/28/2023 | Approved | DAVID SCANTLIN |
| Final | 6/28/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 6/28/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Final | 6/28/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 6/28/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 7/14/2023 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 7/14/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 7/14/2023 | Approved | ALEXANDER HANDY |