8335-8337 N GLADBECK AVE 91324

Certificate Information: 8335-8337 N GLADBECK AVE 91324

Application / Permit
21014-20000-02990
Plan Check / Job No.
B21VN07503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE & 2ND STORY FAMILY ROOM INTO (N) 2-STORY ADU (21'3"x19'6")WITH A (3'-5"x12'-3") 2ND FLOOR ADDITION PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 8/25/2021
Issuing Office
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 PETER MOSESIAN
Corrections Issued 7/17/2021 PETER MOSESIAN
Quality Review Completed 7/30/2021 OMID HEDAYAT
Building Plans Picked Up 7/30/2021 APPLICANT
Plan Check Approved 8/25/2021 PETER MOSESIAN
Issued 8/25/2021 APPLICANT
CofO in Progress 4/14/2022 JEFFREY PARD
Permit Finaled 4/19/2022 JOHN JANSON
CofO Issued 4/19/2022 JOHN JANSON
Permit Finaled 4/19/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/3/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/3/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/3/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/3/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/13/2021 Approved SHAVONNE ESPINOZA
Footing/Foundation/Slab 10/13/2021 Not Ready for Inspection JEFFREY PARD
Pre-Inspection 10/13/2021 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 10/27/2021 Approved JEFFREY PARD
PLUMBING-Rough 10/27/2021 Partial Approval JEFFREY PARD
Insulation 11/4/2021 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Approved JEFFREY PARD
Deputy Wood Construction 11/15/2021 Approved JEFFREY PARD
HVAC-Rough 11/30/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 12/10/2021 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 12/10/2021 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 12/13/2021 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 12/13/2021 Approved JEFFREY PARD
PLUMBING-Rough 12/13/2021 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 12/15/2021 Approved JEFFREY PARD
HVAC-Rough 12/15/2021 Approved JEFFREY PARD
PLUMBING-Rough 12/15/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/16/2021 Approved JEFFREY PARD
Green Building Rough 12/16/2021 Approved JEFFREY PARD
Insulation 12/16/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 12/16/2021 Approved JEFFREY PARD
Drywall Nailing 12/22/2021 Approved MORRIS JACKSON
Shower Pan 1/11/2022 Approved VINCENT HANLEY
Gas Test 3/18/2022 Approved JEFFREY PARD
ELECTRICAL-Final 3/30/2022 Not Ready for Inspection DAVID SCANTLIN
Final 3/30/2022 Corrections Issued DAVID SCANTLIN
Green Building Final 3/30/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 3/30/2022 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Final 3/30/2022 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 3/30/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Final 4/5/2022 Approved JEFFREY PARD
HVAC-Final 4/5/2022 Approved JEFFREY PARD
PLUMBING-Final 4/5/2022 Approved JEFFREY PARD
ELECTRICAL-Final 4/13/2022 Approved JEFFREY PARD
Final 4/13/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 4/13/2022 Approved JEFFREY PARD
HVAC-Final 4/13/2022 Approved JEFFREY PARD
PLUMBING-Final 4/13/2022 Approved JEFFREY PARD
Service/Power Release 4/13/2022 Not Required JEFFREY PARD
Smoke Detectors 4/13/2022 Approved JEFFREY PARD