8519 N KEOKUK AVE 91306
Certificate Information: 8519 N KEOKUK AVE 91306
- Application / Permit
- 21014-20000-02965
- Plan Check / Job No.
- B21VN07442
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (16'-0"x 20'-5") 327 SQ. FT. TO REAR OF (E) SFD. PER WFPP
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofO Issued on 7/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2021 | PETER MOSESIAN |
| Corrections Issued | 6/15/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| Plan Check Approved | 7/27/2021 | PETER MOSESIAN |
| Issued | 7/27/2021 | APPLICANT |
| CofO in Progress | 7/6/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 7/20/2022 | JOHN JANSON |
| Permit Finaled | 7/20/2022 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/23/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2021 | Partial Inspection | DAVID STEPANYAN |
| Sewer | 8/10/2021 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 8/16/2021 | Corrections Issued | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Corrections Issued | DAVID STEPANYAN |
| Pre-Inspection | 8/18/2021 | Partial Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 9/8/2021 | Corrections Issued | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 9/16/2021 | Conditional Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 9/17/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 9/17/2021 | Partial Approval | DAVID STEPANYAN |
| Sewer | 9/17/2021 | Partial Approval | DAVID STEPANYAN |
| Deputy Wood Construction | 9/24/2021 | Conditional Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 9/24/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/1/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/15/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 10/15/2021 | Approved | TROY SANDERS |
| Green Building Rough | 10/15/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 10/15/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/15/2021 | Approved | TROY SANDERS |
| Insulation | 10/21/2021 | Corrections Issued | STEVEN BACK |
| Drywall Nailing | 10/25/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 12/2/2021 | Approved | JAVIER RAMOS JR |
| Final | 6/7/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 6/7/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/7/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Final | 7/5/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 7/5/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/5/2022 | Approved | CHRIS CHRISTENSEN |