13722 W BRANFORD ST 91331

Certificate Information: 13722 W BRANFORD ST 91331

Application / Permit
21014-20000-02957
Plan Check / Job No.
B21VN07427
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 265 SQ. FT RECREATION ROOM ADDITION ON TOP OF EXISTING GARAGE PER ENGINEERING.
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
CofO Issued on 6/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 COLIN LOREDO
Corrections Issued 7/19/2021 COLIN LOREDO
Quality Review Completed 7/30/2021 OMID HEDAYAT
Building Plans Picked Up 8/3/2021 APPLICANT
Plan Check Approved 8/19/2021 COLIN LOREDO
Issued 10/19/2021 APPLICANT
CofO in Progress 4/26/2022 GREGG CUMMINGS
Permit Finaled 6/11/2022 DANIEL ORRANTE
CofO Issued 6/11/2022 DANIEL ORRANTE
Permit Finaled 6/11/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/11/2021 DAGOVERTO GUERRERO
ZA Case Cleared 8/11/2021 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 8/12/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/22/2021 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Not Ready for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 10/22/2021 Not Ready for Inspection GREGG CUMMINGS
Sewer 10/22/2021 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/27/2021 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 10/27/2021 Approved GREGG CUMMINGS
Deputy Reinf. Concrete 10/29/2021 Conditional Approval WILLIAM WREN
BUILDING-Rough-Frame 11/24/2021 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Approved WILLIAM WREN
Green Building Rough 11/24/2021 Not Ready for Inspection WILLIAM WREN
Wood Frame 11/24/2021 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 12/6/2021 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 12/6/2021 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 12/6/2021 Not Ready for Inspection GREGG CUMMINGS
Sewer 12/6/2021 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 12/10/2021 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 12/10/2021 Approved GREGG CUMMINGS
Underground Mechanical 12/10/2021 Approved GREGG CUMMINGS
Wood Frame 12/10/2021 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 12/22/2021 Partial Approval DAVID MATSON
Green Building Rough 12/22/2021 Approved DAVID MATSON
Insulation 12/22/2021 Not Ready for Inspection DAVID MATSON
Wood Frame 12/22/2021 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 1/11/2022 Corrections Issued GREGG CUMMINGS
Insulation 1/11/2022 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 1/11/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 1/21/2022 Approved GREGG CUMMINGS
Green Building Rough 1/21/2022 Approved GREGG CUMMINGS
Insulation 1/21/2022 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 1/21/2022 Approved GREGG CUMMINGS
Drywall Nailing 1/28/2022 Approved GREGG CUMMINGS
Final 4/5/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 4/5/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 4/5/2022 Approved GREGG CUMMINGS
Final 4/15/2022 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved GREGG CUMMINGS
ELECTRICAL-Final 4/25/2022 Approved GREGG CUMMINGS
Final 4/25/2022 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 4/25/2022 Approved GREGG CUMMINGS
PLUMBING-Final 4/25/2022 Approved GREGG CUMMINGS