3849 N HOLLYPARK PL 90039

Certificate Information: 3849 N HOLLYPARK PL 90039

Application / Permit
21014-20000-02955
Plan Check / Job No.
B21VN07425
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 12' X 18' ADDITION FOR (N) BEDROOM AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 04/14/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/2/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2021 APPLICANT
Assigned to Plan Check Engineer 6/15/2021 RAPHAEL ROSAS
Corrections Issued 6/15/2021 RAPHAEL ROSAS
Applicant returned to address corrections 8/30/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/11/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/29/2021 RAPHAEL ROSAS
Building Plans Picked Up 1/10/2022 APPLICANT
Plan Check Approved 1/11/2022 RAPHAEL ROSAS
Issued 6/2/2022 APPLICANT
CofO in Progress 5/30/2024 COREY HUPP
Permit Finaled 6/14/2024 DANIEL SANCHEZ
CofO Issued 6/14/2024 DANIEL SANCHEZ
Permit Finaled 6/14/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/5/2021 STEVE MELGAR
Sewer availability Cleared 8/5/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/6/2021 STEVE MELGAR

Contact Information

Contractor Diehl William K; Lic. No.: 1075261-B 4110 RINCON AVENUE      MONTROSE, CA 91020
Engineer Luisoni,, Antonio Stefano; Lic. No.: S1781 12757 DEON PLACE      GRANADA HILLS, CA 91344

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/26/2022 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Corrections Issued COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 12/7/2022 Partial Approval COREY HUPP
Interior/Exterior Lathing 2/14/2023 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 2/17/2023 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 3/3/2023 Partial Approval COREY HUPP
Interior/Exterior Lathing 3/7/2023 Partial Approval COREY HUPP
ELECTRICAL-Rough 5/11/2023 Partial Approval COREY HUPP
Insulation 6/9/2023 Approved HAGOP BADOSSIAN
Smoke Detectors 6/15/2023 Not Ready for Inspection COREY HUPP
Rough-Elec/Plmb/HVAC 6/20/2023 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 6/23/2023 Approved COREY HUPP
Smoke Detectors 6/23/2023 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 12/20/2023 Approved COREY HUPP
HVAC-Rough 12/20/2023 Approved COREY HUPP
HVAC-Final 4/9/2024 Approved COREY HUPP
Smoke Detectors 4/9/2024 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 5/24/2024 Approved COREY HUPP
Final 5/24/2024 OK to Issue CofO COREY HUPP
Footing/Foundation/Slab 5/24/2024 Approved COREY HUPP
Green Building Final 5/24/2024 Approved COREY HUPP
Green Building Rough 5/24/2024 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 5/24/2024 SGSOV Approved COREY HUPP
Smoke Detectors 5/24/2024 Approved COREY HUPP