16023 W DEVONSHIRE ST 91344
Certificate Information: 16023 W DEVONSHIRE ST 91344
- Application / Permit
- 21014-20000-02947
- Plan Check / Job No.
- B21VN07369
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 7' X 16'9" TO THE (E) SFD TO CREATE NEW BATHROOM AND TO EXTEND THE LIVING ROOM, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/14/2021
- Issuing Office
- Current Status
- CofO Issued on 6/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2021 | RARES BODEA |
| Corrections Issued | 6/15/2021 | RARES BODEA |
| Applicant returned to address corrections | 12/10/2021 | RARES BODEA |
| Plan Check Approved | 12/14/2021 | RARES BODEA |
| Issued | 12/14/2021 | APPLICANT |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| CofO in Progress | 6/6/2024 | ROBERT GOLD |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
| CofO Issued | 6/21/2024 | RUBEN SALAS |
| Permit Finaled | 6/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/9/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/29/2023 | Conditional Approval | MICHAEL SMITH |
| PLUMBING-Rough | 6/30/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 6/30/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/28/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/28/2024 | Approved | JAVIER RAMOS JR |
| Final | 3/28/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/28/2024 | Approved | JAVIER RAMOS JR |
| Green Building Final | 3/28/2024 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/28/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 3/28/2024 | Approved | JAVIER RAMOS JR |
| Final | 5/31/2024 | Partial Approval | ROBERT GOLD |
| Final | 6/6/2024 | OK to Issue CofO | ROBERT GOLD |