5834 N CORBIN AVE 91356

Certificate Information: 5834 N CORBIN AVE 91356

Application / Permit
21014-20000-02945
Plan Check / Job No.
B21VN07362
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL WITH ADDITION, WITH ONLY 1 WALL (6'-9" TOTAL LINEAR FEET) TO REMAIN. NEW OVERALL BUILDING DIMENSIONS: 90'7" X 55'2" WITH ATTACHED GARAGE, 20'3"X34'7" ATTACHED TRELLIS, AND 19'1"X24'8" ATTACHED REAR PATIO NFPA 13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/31/2022
Issuing Office
Current Status
CofO Issued on 1/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 MARVEL DELACRUZ
Corrections Issued 7/28/2021 MARVEL DELACRUZ
Quality Review Completed 8/2/2021 OMID HEDAYAT
Applicant returned to address corrections 2/10/2022 MARVEL DELACRUZ
Applicant returned to address corrections 3/11/2022 MARVEL DELACRUZ
Plan Check Approved 3/23/2022 RAPHAEL ROSAS
Issued 3/31/2022 APPLICANT
CofO in Progress 12/21/2022 SEAN HAUPT
CofO Issued 1/10/2023 MICHAEL SMITH
Permit Finaled 1/10/2023 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 8/26/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/31/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/31/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 10/11/2021 MATTHEW CRAIG
Low Impact Development Cleared 12/15/2021 KHAING AYE
Trees in Parkway Cleared 1/25/2022 ADALBERTO VERA
Roof/Waste drainage to street Cleared 1/26/2022 DAGOVERTO GUERRERO
Green Code Cleared 3/23/2022 MARVEL DELACRUZ
Hold Cleared 5/5/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2022 Partial Approval PETER FOLLING
Excavation/Setback/Form/Re-Bar 4/8/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 4/8/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Approved SEAN HAUPT
Deputy Wood Construction 5/13/2022 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/26/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 5/26/2022 Not Ready for Inspection SEAN HAUPT
Sewer 5/26/2022 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 6/14/2022 Conditional Approval SEAN HAUPT
ELECTRICAL-Rough 6/14/2022 Approved SEAN HAUPT
Green Building Rough 6/14/2022 Approved SEAN HAUPT
HVAC-Rough 6/14/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 6/14/2022 Approved SEAN HAUPT
PLUMBING-Rough 6/14/2022 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 6/14/2022 Approved SEAN HAUPT
Insulation 6/23/2022 Approved SEAN HAUPT
Shower Pan 6/23/2022 Approved SEAN HAUPT
Drywall Nailing 7/6/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 7/6/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 7/18/2022 Approved MORRIS JACKSON
Pre-Inspection 8/2/2022 Partial Approval SEAN HAUPT
Underground Mechanical 9/6/2022 Conditional Approval SEAN HAUPT
BUILDING-Rough-Frame 12/12/2022 Approved SEAN HAUPT
Final 12/12/2022 Corrections Issued SEAN HAUPT
Green Building Final 12/12/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 12/12/2022 Not Ready for Inspection SEAN HAUPT
Final 12/20/2022 OK to Issue CofO SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Approved SEAN HAUPT
Service/Power Release 12/20/2022 Approved SEAN HAUPT
Smoke Detectors 12/20/2022 Approved SEAN HAUPT