218 N STRADA CORTA ROAD 90077

Certificate Information: 218 N STRADA CORTA ROAD 90077

Application / Permit
21014-20000-02944
Plan Check / Job No.
B21VN07351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (26'-6"x 10'-6") BATHROOM/CLOSET, (30'-0"x 18'-0") IRR SHAPE LAUNDRY/ FITNESS RM @ 1ST FLOOR AND ADD (27'-7"x 20'-4") STUDY, DRESSING RM/EXPAND MASTER BATH @ 2ND FLOOR AND REMODEL TO EXISTING 2 STORY S.F.D. WORK PER ENGINEER.
Permit Issued
Issued on 10/13/2021
Issuing Office
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 TROY DEGUZMAN
Corrections Issued 6/27/2021 TROY DEGUZMAN
Quality Review Completed 6/29/2021 OMID HEDAYAT
Building Plans Picked Up 7/6/2021 APPLICANT
Applicant returned to address corrections 10/4/2021 TROY DEGUZMAN
Plan Check Approved 10/13/2021 TROY DEGUZMAN
Issued 10/13/2021 APPLICANT
CofO in Progress 2/24/2023 CHRISTOPHER WILSON
CofO in Progress 2/24/2023 CHRISTOPHER WILSON
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/13/2021 TRACY TATE
BHO/Hillside ordinance Cleared 7/13/2021 TRACY TATE
BHO/Hillside ordinance Cleared 7/13/2021 TRACY TATE
BHO/Hillside ordinance Cleared 7/13/2021 TRACY TATE
BHO/Hillside ordinance Cleared 7/13/2021 TRACY TATE
BHO/Hillside ordinance Cleared 7/13/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 7/13/2021 TRACY TATE
Sewer availability Cleared 7/13/2021 TRACY TATE
ZI Cleared 7/13/2021 LOUIS ORTEGA
Hydrant and Access approval Cleared 8/1/2021 ROBERT DUFF
Low Impact Development Cleared 9/9/2021 TA ANH
Roof/Waste drainage to street Cleared 9/10/2021 DINAH GARIN
GPI Written Notices Cleared 10/4/2021 TROY DEGUZMAN
Grading Pre-Inspection Cleared 10/4/2021 TROY DEGUZMAN
Green Code Cleared 10/4/2021 TROY DEGUZMAN

Contact Information

Architect Rios,, Mark William; Lic. No.: C15744 3101 W EXPOSITION PLACE      LOS ANGELES, CA 90018
Contractor Holz Richard Inc; Lic. No.: 294504-B 520 S SEPULVEDA BLVD #407      LOS ANGELES, CA 90049
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/20/2021 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 10/20/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/25/2021 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 10/25/2021 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 10/27/2021 Approved CHRISTOPHER WILSON
Sewer 11/1/2021 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 11/18/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 12/7/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 12/7/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/13/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/18/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 2/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 2/24/2022 Approved CHRISTOPHER WILSON
HVAC-Rough 2/25/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 2/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 3/1/2022 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 3/3/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/7/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 3/8/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 3/16/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 3/16/2022 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 3/16/2022 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Rough 3/18/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/21/2022 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 3/21/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 3/23/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 3/25/2022 Partial Approval CHRISTOPHER WILSON
Insulation 4/4/2022 Approved CHRISTOPHER WILSON
PLUMBING-Rough 4/7/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 4/7/2022 Approved CHRISTOPHER WILSON
Drywall Nailing 4/19/2022 Partial Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 4/19/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 11/3/2022 Approved CHRISTOPHER WILSON
Shower Pan 11/3/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 11/9/2022 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 11/15/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 12/1/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 12/2/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 12/12/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 12/14/2022 Approved CHRISTOPHER WILSON
PLUMBING-Final 12/15/2022 Approved CHRISTOPHER WILSON
HVAC-Final 12/22/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/4/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 1/4/2023 Approved CHRISTOPHER WILSON
Final 1/4/2023 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 1/4/2023 Approved CHRISTOPHER WILSON
Green Building Final 1/4/2023 Approved CHRISTOPHER WILSON
Green Building Rough 1/4/2023 Approved CHRISTOPHER WILSON
HVAC-Final 1/4/2023 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 1/4/2023 Approved CHRISTOPHER WILSON
Final 2/3/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 2/3/2023 Approved CHRISTOPHER WILSON
Final 2/7/2023 Not Ready for Inspection STEPHANIE SWANSON
Final 2/22/2023 OK to Issue CofO CHRISTOPHER WILSON