- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- CofO Issued on 2/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | TROY DEGUZMAN |
| Corrections Issued | 6/27/2021 | TROY DEGUZMAN |
| Quality Review Completed | 6/29/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/6/2021 | APPLICANT |
| Applicant returned to address corrections | 10/4/2021 | TROY DEGUZMAN |
| Plan Check Approved | 10/13/2021 | TROY DEGUZMAN |
| Issued | 10/13/2021 | APPLICANT |
| CofO in Progress | 2/24/2023 | CHRISTOPHER WILSON |
| CofO in Progress | 2/24/2023 | CHRISTOPHER WILSON |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
| CofO Issued | 2/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 7/13/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | TRACY TATE |
| Sewer availability | Cleared | 7/13/2021 | TRACY TATE |
| ZI | Cleared | 7/13/2021 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 8/1/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 9/9/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 9/10/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 10/4/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 10/4/2021 | TROY DEGUZMAN |
| Green Code | Cleared | 10/4/2021 | TROY DEGUZMAN |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: C15744 | 3101 W EXPOSITION PLACE LOS ANGELES, CA 90018 |
| Contractor | Holz Richard Inc; Lic. No.: 294504-B | 520 S SEPULVEDA BLVD #407 LOS ANGELES, CA 90049 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/20/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 10/20/2021 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/25/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/25/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/27/2021 | Approved | CHRISTOPHER WILSON |
| Sewer | 11/1/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Underground Mechanical | 11/18/2021 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/7/2021 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 12/7/2021 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/18/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 2/24/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 2/24/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/24/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 2/25/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 2/28/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/1/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 3/3/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/7/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/8/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/16/2022 | Partial Inspection | MICHAEL PELHAM |
| Special/Order Compliance | 3/16/2022 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/18/2022 | Approved | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/21/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Green Building Rough | 3/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Final | 3/23/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 3/24/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/25/2022 | Partial Approval | CHRISTOPHER WILSON |
| Insulation | 4/4/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/7/2022 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 4/7/2022 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 4/19/2022 | Partial Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 11/3/2022 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 11/3/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 11/9/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Service/Power Release | 11/15/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 12/1/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 12/2/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 12/12/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 12/14/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 12/15/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 12/22/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 1/4/2023 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 1/4/2023 | Approved | CHRISTOPHER WILSON |
| Final | 1/4/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 1/4/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 1/4/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 1/4/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 1/4/2023 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 1/4/2023 | Approved | CHRISTOPHER WILSON |
| Final | 2/3/2023 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 2/3/2023 | Approved | CHRISTOPHER WILSON |
| Final | 2/7/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Final | 2/22/2023 | OK to Issue CofO | CHRISTOPHER WILSON |