2110 W HILL DR 90041
Certificate Information: 2110 W HILL DR 90041
- Application / Permit
- 21014-20000-02934
- Plan Check / Job No.
- B21VN07333
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL WITH 6'3"X46'10" 1ST STORY ADDITION TO (E) SFD.
- Permit Issued
- Issued on 12/29/2021
- Issuing Office
- Current Status
- CofO Issued on 4/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | MARVEL DELACRUZ |
| Corrections Issued | 7/10/2021 | MARVEL DELACRUZ |
| Quality Review Completed | 7/16/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/20/2021 | APPLICANT |
| Applicant returned to address corrections | 10/27/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 11/22/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 12/20/2021 | MARVEL DELACRUZ |
| Issued | 12/29/2021 | APPLICANT |
| CofO in Progress | 4/30/2025 | BRENDAN MORELLI |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
| CofO Issued | 4/30/2025 | DEROLD HAUFF |
| Permit Finaled | 4/30/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/28/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/28/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 9/13/2021 | BRIAN MILLER |
| Green Code | Cleared | 10/27/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick Edward; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 8/10/2022 | Conditional Approval | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 8/11/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Approved | CRAIG VAUGHAN |
| Special/Order Compliance | 9/15/2022 | Corrections Issued | RUBEN SALAS |
| Posting Pre-Inspection | 9/16/2022 | Approved | RUBEN SALAS |
| Special/Order Compliance | 9/22/2022 | Corrections Issued | CRAIG VAUGHAN |
| Deputy Steel/Welding | 12/8/2022 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/2/2023 | Conditional Approval | BRIAN SULLIVAN |
| Green Building Rough | 6/2/2023 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 6/2/2023 | Conditional Approval | BRIAN SULLIVAN |
| Insulation | 7/7/2023 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 7/7/2023 | Partial Approval | JEFFREY MEAD |
| Insulation | 7/13/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/29/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/12/2023 | Approved | CRAIG VAUGHAN |
| Shower Pan | 12/12/2023 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 12/20/2023 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 4/24/2025 | Approved | BRENDAN MORELLI |
| Final | 4/24/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 4/24/2025 | Approved | BRENDAN MORELLI |
| Gas Test | 4/24/2025 | Approved | BRENDAN MORELLI |
| Green Building Final | 4/24/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 4/24/2025 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 4/24/2025 | Approved | BRENDAN MORELLI |
| Final | 4/28/2025 | OK to Issue CofO | BRENDAN MORELLI |