1715 W 42ND ST 90062
Certificate Information: 1715 W 42ND ST 90062
- Application / Permit
- 21014-20000-02933
- Plan Check / Job No.
- B21VN07331
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 29' X 30'-5" ADDITION TO (E) DETACHED GARAGE FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/9/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/13/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 6/10/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/14/2022 | APPLICANT |
| Issued | 6/9/2023 | APPLICANT |
| CofO in Progress | 3/3/2025 | SABAS ALONSO |
| Permit Finaled | 3/3/2025 | DEROLD HAUFF |
| CofO Issued | 3/3/2025 | DEROLD HAUFF |
| Permit Finaled | 3/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2021 | CELINA MORENO |
| Low Impact Development | Cleared | 5/27/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 6/1/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | CELINA MORENO |
| Sewer availability | Cleared | 6/2/2022 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 4/11/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/11/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2024 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 5/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/6/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 5/6/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 5/6/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 5/6/2024 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/21/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 5/21/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 5/21/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 5/21/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/21/2024 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 5/21/2024 | Approved | SABAS ALONSO |
| Insulation | 5/24/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/29/2024 | Approved | JOSH MEISTER |
| Shower Pan | 5/29/2024 | Approved | JOSH MEISTER |
| Final | 8/21/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 8/21/2024 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 8/21/2024 | Approved | SABAS ALONSO |
| Final | 1/27/2025 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 1/27/2025 | Approved | SABAS ALONSO |
| Final | 2/25/2025 | OK to Issue CofO | SABAS ALONSO |