4629 N ETHEL AVE 91423

Certificate Information: 4629 N ETHEL AVE 91423

Application / Permit
21014-20000-02900
Plan Check / Job No.
B21VN07269
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 18'-2" DETACHED GARAGE AND ADD 15' X 15'-5" TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 2/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2021 APPLICANT
Assigned to Plan Check Engineer 6/11/2021 RAPHAEL ROSAS
Corrections Issued 6/14/2021 RAPHAEL ROSAS
Plan Check Approved 10/14/2021 RAPHAEL ROSAS
Building Plans Picked Up 10/25/2021 APPLICANT
Issued 11/3/2021 APPLICANT
CofO in Progress 2/1/2023 CHRISTOPHE COCHRAN
CofO in Progress 2/1/2023 CHRISTOPHE COCHRAN
CofO Issued 2/2/2023 MICHAEL SMITH
Permit Finaled 2/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/24/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/24/2021 DAGOVERTO GUERRERO
ZI Cleared 6/24/2021 LAUREN PADICK
Sewer availability Cleared 6/29/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/31/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 10/13/2021 WALTER RAMIREZ

Contact Information

Contractor Platinum Home Remodeling Inc; Lic. No.: 1060535-B 12444 VICTORY BLVD #402      VALLEY GLEN, CA 91606
Engineer Hsiao,, Stephanie; Lic. No.: C75937 255 N MICHIGAN AVE #5      PASADENA, CA 91106

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/15/2021 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 11/18/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Approved ARAM AVEDISIAN
MERV13>=Rough 12/7/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/7/2021 Approved ARAM AVEDISIAN
Sewer 12/7/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/10/2021 Approved ARAM AVEDISIAN
HVAC-Rough 12/10/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/14/2021 Partial Approval ARAM AVEDISIAN
Insulation 12/17/2021 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 12/22/2021 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 12/22/2021 Corrections Issued ARAM AVEDISIAN
Shower Pan 12/22/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 12/28/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/26/2022 Approved ARAM AVEDISIAN
Final 4/26/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 4/26/2022 Approved ARAM AVEDISIAN
Green Building Rough 4/26/2022 Approved ARAM AVEDISIAN
MERV13>=Final 4/26/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 4/26/2022 Approved ARAM AVEDISIAN
Final 5/3/2022 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Not Ready ARAM AVEDISIAN
Final 5/9/2022 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 5/9/2022 SGSOV Approved ARAM AVEDISIAN
Final 5/13/2022 Corrections Issued ARAM AVEDISIAN
Final 7/13/2022 Conditional Approval CHRISTOPHE COCHRAN
Final 2/1/2023 OK to Issue CofO CHRISTOPHE COCHRAN