6145 N LOCKHURST DR 91367
Certificate Information: 6145 N LOCKHURST DR 91367
- Application / Permit
- 21014-20000-02899
- Plan Check / Job No.
- B21VN07267
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL 235 SQ. FT. ADDITION OF A NEW BEDROOM AND WALK IN CLOSET, AND A 161 SQ. FT. MASTER BEDROOM AND WALK IN CLOSET ADDITION TO THE (E) SFD. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/10/2021 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/24/2021 | LUISANGEL VALENZUELA |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 2/3/2022 | TROY SANDERS |
| Permit Finaled | 3/11/2022 | JOHN JANSON |
| CofO Issued | 3/11/2022 | JOHN JANSON |
| Permit Finaled | 3/11/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/16/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Hua-Hsing; Lic. No.: C35695 | 27800 MOUNT HOOD YORBA LINDA, CA 92887 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/11/2021 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 8/13/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 8/26/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 9/7/2021 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Approved | PETER FOLLING |
| HVAC-Rough | 9/7/2021 | Approved | PETER FOLLING |
| PLUMBING-Rough | 9/7/2021 | Corrections Issued | PETER FOLLING |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | TROY SANDERS |
| Green Building Rough | 9/15/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/15/2021 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 9/15/2021 | Approved | TROY SANDERS |
| Shower Pan | 9/15/2021 | Approved | TROY SANDERS |
| Insulation | 9/22/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 9/22/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 9/23/2021 | Approved | HENRY KIM |
| Drywall Nailing | 9/28/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Not Ready | JEFFREY PARD |
| Final | 2/2/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 2/2/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 2/2/2022 | Approved | TROY SANDERS |