1819 W 83RD ST 90047

Certificate Information: 1819 W 83RD ST 90047

Application / Permit
21014-20000-02891
Plan Check / Job No.
B21VN07239
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 12' X 12' REAR ADDITION TO THE (E) SFD. ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/22/2021
Issuing Office
Current Status
CofO Issued on 2/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 LUISANGEL VALENZUELA
Corrections Issued 6/10/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 6/17/2021 LUISANGEL VALENZUELA
Issued 6/22/2021 APPLICANT
Building Plans Picked Up 6/23/2021 APPLICANT
CofO in Progress 3/7/2022 FREDDIE RIVERA
Permit Finaled 2/16/2023 DANIEL ORRANTE
CofO Issued 2/16/2023 DANIEL ORRANTE
Permit Finaled 2/16/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/17/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 6/17/2021 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/15/2021 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 7/22/2021 Approved HORACE FULTZ
BUILDING-Rough-Frame 8/10/2021 Partial Approval FREDDIE RIVERA
Green Building Rough 8/10/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 8/10/2021 Partial Approval FREDDIE RIVERA
Wood Frame 8/10/2021 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/21/2021 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 9/21/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Partial Approval FREDDIE RIVERA
Green Building Rough 9/21/2021 No Access for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/24/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Approved FREDDIE RIVERA
Green Building Rough 9/24/2021 Approved FREDDIE RIVERA
Insulation 9/24/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 9/24/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/13/2021 Approved FREDDIE RIVERA
Green Building Final 12/17/2021 Corrections Issued FREDDIE RIVERA
Green Building Final 1/24/2022 Approved FREDDIE RIVERA
Final 3/7/2022 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 3/7/2022 Approved FREDDIE RIVERA