8501 W BRIER DR 90046
Certificate Information: 8501 W BRIER DR 90046
- Application / Permit
- 21014-20000-02882
- Plan Check / Job No.
- B21VN07191
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, (N) 7'-9" X 4'-3" ADDITION TO FIRST FLOOR TO ENCLOSE (E) UTILITY ROOM AND (N) 7'-5" X 14'-2" ADDITION TO MASTER BATHROOM, 6'-7" X 8'-3" ADDITION TO BATHROOM ON SECOND FLOOR AND (N) 3'-8" X 7'-2" OVERHANG ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 1/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 7/23/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 7/26/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/25/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 8/30/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/15/2021 | APPLICANT |
| Building Plans Picked Up | 9/30/2021 | APPLICANT |
| No Progress | 1/2/2025 | DEROLD HAUFF |
| CofO in Progress | 1/2/2025 | DEROLD HAUFF |
| CofO in Progress | 1/4/2025 | RAUL BARAJAS |
| Permit Finaled | 1/10/2025 | DEROLD HAUFF |
| CofO Issued | 1/10/2025 | DEROLD HAUFF |
| Permit Finaled | 1/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/9/2021 | JEANIE LAM |
| Sewer availability | Cleared | 8/9/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 8/30/2021 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Architect | Tomalevski,, Vladimir Bogdanov; Lic. No.: C22417 | 8416 HAROLD WAY L&V TOMALEVSKI ARCHITECTS, INC. LOS ANGELES, CA 90069 |
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/18/2021 | Corrections Issued | RAUL BARAJAS |
| Deck | 11/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 11/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 11/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 11/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 11/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 11/24/2021 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 11/24/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 12/6/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 12/6/2021 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 2/3/2022 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 9/8/2023 | No Access for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/16/2023 | No Access for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 10/16/2023 | No Access for Inspection | STUART CHAPMAN |
| Final | 10/16/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/16/2023 | No Access for Inspection | STUART CHAPMAN |
| Green Building Final | 10/16/2023 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 10/16/2023 | No Access for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/17/2023 | No Access for Inspection | RAUL BARAJAS |
| Wood Frame | 11/17/2023 | No Access for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 1/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 1/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Insulation | 1/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 1/8/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/18/2024 | Partial Inspection | RAUL BARAJAS |
| Pre-Inspection | 9/18/2024 | Partial Inspection | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 9/20/2024 | Conditional Approval | BRIAN SULLIVAN |
| Pre-Inspection | 9/26/2024 | Partial Inspection | RAUL BARAJAS |
| Pre-Inspection | 9/30/2024 | Partial Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/3/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 10/4/2024 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/7/2024 | Approved | RAUL BARAJAS |
| Wood Frame | 10/15/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 10/21/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Approved | ROY SPAULDING |
| Insulation | 10/25/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 10/30/2024 | Approved | RAUL BARAJAS |
| Shower Pan | 11/6/2024 | Approved | NICHOLAS LOPEZ |
| Final | 12/10/2024 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/10/2024 | Approved | RAUL BARAJAS |
| Green Building Final | 12/10/2024 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/10/2024 | Approved | RAUL BARAJAS |
| Final | 12/18/2024 | Not Ready for Inspection | ROY SPAULDING |
| Final | 1/3/2025 | OK to Issue CofO | RAUL BARAJAS |