8501 W BRIER DR 90046

Certificate Information: 8501 W BRIER DR 90046

Application / Permit
21014-20000-02882
Plan Check / Job No.
B21VN07191
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, (N) 7'-9" X 4'-3" ADDITION TO FIRST FLOOR TO ENCLOSE (E) UTILITY ROOM AND (N) 7'-5" X 14'-2" ADDITION TO MASTER BATHROOM, 6'-7" X 8'-3" ADDITION TO BATHROOM ON SECOND FLOOR AND (N) 3'-8" X 7'-2" OVERHANG ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
CofO Issued on 1/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/23/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/26/2021 OMID HEDAYAT
Applicant returned to address corrections 8/25/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/30/2021 SEWADA ZADOORAN MILAGARDI
Issued 9/15/2021 APPLICANT
Building Plans Picked Up 9/30/2021 APPLICANT
No Progress 1/2/2025 DEROLD HAUFF
CofO in Progress 1/2/2025 DEROLD HAUFF
CofO in Progress 1/4/2025 RAUL BARAJAS
Permit Finaled 1/10/2025 DEROLD HAUFF
CofO Issued 1/10/2025 DEROLD HAUFF
Permit Finaled 1/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/9/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 8/9/2021 JEANIE LAM
Sewer availability Cleared 8/9/2021 JEANIE LAM
Grading Pre-Inspection Cleared 8/30/2021 SEWADA ZADOORAN MILAGARDI

Contact Information

Architect Tomalevski,, Vladimir Bogdanov; Lic. No.: C22417 8416 HAROLD WAY   L&V TOMALEVSKI ARCHITECTS, INC.    LOS ANGELES, CA 90069
Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/18/2021 Corrections Issued RAUL BARAJAS
Deck 11/18/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 11/18/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 11/18/2021 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 11/18/2021 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 11/18/2021 Not Ready for Inspection RAUL BARAJAS
Wood Frame 11/18/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 11/24/2021 Approved RAUL BARAJAS
PLUMBING-Rough 11/24/2021 Approved RAUL BARAJAS
Drywall Nailing 12/6/2021 Approved RAUL BARAJAS
Green Building Rough 12/6/2021 Approved RAUL BARAJAS
Special/Order Compliance 2/3/2022 Approved RAUL BARAJAS
Special/Order Compliance 9/8/2023 No Access for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 10/16/2023 No Access for Inspection STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 10/16/2023 No Access for Inspection STUART CHAPMAN
Final 10/16/2023 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 10/16/2023 No Access for Inspection STUART CHAPMAN
Green Building Final 10/16/2023 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 10/16/2023 No Access for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 11/17/2023 No Access for Inspection RAUL BARAJAS
Wood Frame 11/17/2023 No Access for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 1/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Final 1/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 1/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 1/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Insulation 1/8/2024 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 1/8/2024 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/18/2024 Partial Inspection RAUL BARAJAS
Pre-Inspection 9/18/2024 Partial Inspection RAUL BARAJAS
Deputy Drilled-In Anchors 9/20/2024 Conditional Approval BRIAN SULLIVAN
Pre-Inspection 9/26/2024 Partial Inspection RAUL BARAJAS
Pre-Inspection 9/30/2024 Partial Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/3/2024 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 10/4/2024 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/7/2024 Approved RAUL BARAJAS
Wood Frame 10/15/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Rough-Elec/Plmb/HVAC 10/21/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/23/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Approved ROY SPAULDING
Insulation 10/25/2024 Approved JOSH MEISTER
Drywall Nailing 10/30/2024 Approved RAUL BARAJAS
Shower Pan 11/6/2024 Approved NICHOLAS LOPEZ
Final 12/10/2024 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 12/10/2024 Approved RAUL BARAJAS
Green Building Final 12/10/2024 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/10/2024 SGSOV Approved RAUL BARAJAS
Smoke Detectors 12/10/2024 Approved RAUL BARAJAS
Final 12/18/2024 Not Ready for Inspection ROY SPAULDING
Final 1/3/2025 OK to Issue CofO RAUL BARAJAS