1333 E 48TH ST 90011
Certificate Information: 1333 E 48TH ST 90011
- Application / Permit
- 21014-20000-02852
- Plan Check / Job No.
- B21VN07116
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 22'-10" X 20' ADDITION OF A BEDROOM AND BATHROOM TO THE (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Current Status
- CofO Issued on 8/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2021 | SERGIO MUNIZ |
| Corrections Issued | 6/16/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 3/12/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 3/31/2022 | APPLICANT |
| Plan Check Approved | 5/13/2022 | SERGIO MUNIZ |
| Issued | 5/25/2022 | APPLICANT |
| CofO in Progress | 8/19/2023 | ALEJANDRO DE ARTOLA |
| CofO Issued | 8/28/2023 | DEROLD HAUFF |
| Permit Finaled | 8/28/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/16/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 5/2/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/14/2023 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/14/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/22/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/19/2023 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 4/19/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 4/19/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2023 | Corrections Issued | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 5/16/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 5/31/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/31/2023 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | BRENDAN MORELLI |
| Green Building Rough | 6/8/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 6/8/2023 | Approved | BRENDAN MORELLI |
| Insulation | 6/15/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 6/26/2023 | Approved | BRENDAN MORELLI |
| Shower Pan | 6/26/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/5/2023 | Approved | BRENDAN MORELLI |
| Final | 8/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/2/2023 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/2/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/18/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/18/2023 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 8/18/2023 | Approved | ALEJANDRO DE ARTOLA |