6053 N COLFAX AVE 91606
Certificate Information: 6053 N COLFAX AVE 91606
- Application / Permit
- 21014-20000-02849
- Plan Check / Job No.
- B21VN07101
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (eplan) CONVERTING EXISTING GARAGE TO AN ACCESSORY DWELLING UNIT AND 2ND STORY ADDITION PER LAMC 12.22.A.33 (c) and (d).
- Permit Issued
- Issued on 5/9/2023
- Issuing Office
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | YOUNG KIM |
| Corrections Issued | 7/28/2021 | YOUNG KIM |
| Quality Review Completed | 8/10/2021 | WING SUEN |
| Applicant returned to address corrections | 3/7/2023 | YOUNG KIM |
| Applicant returned to address corrections | 3/9/2023 | YOUNG KIM |
| Applicant returned to address corrections | 3/29/2023 | YOUNG KIM |
| Applicant returned to address corrections | 4/7/2023 | YOUNG KIM |
| Applicant returned to address corrections | 4/19/2023 | YOUNG KIM |
| Plan Check Approved | 5/3/2023 | YOUNG KIM |
| Issued | 5/9/2023 | APPLICANT |
| CofO in Progress | 3/27/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
| CofO Issued | 4/17/2025 | RUBEN SALAS |
| Permit Finaled | 4/17/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 6/3/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/3/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/1/2023 | ERNEST TSE |
| Sewer availability | Cleared | 2/9/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/18/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 6/16/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Underground Mechanical | 6/16/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Sewer | 6/23/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Underground Mechanical | 6/23/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/29/2023 | Approved | JOHN HAYES |
| Underground Mechanical | 6/29/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 7/21/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 8/17/2023 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 8/17/2023 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/17/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/17/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 9/1/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 9/1/2023 | Approved | JOHN HAYES |
| PLUMBING-Rough | 9/1/2023 | Approved | JOHN HAYES |
| Shower Pan | 9/1/2023 | Approved | JOHN HAYES |
| Insulation | 9/7/2023 | Corrections Issued | JOHN HAYES |
| Insulation | 9/12/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 9/15/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 11/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 11/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 11/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 11/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/8/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 1/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 1/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 1/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 1/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 1/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 1/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 1/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/7/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 2/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 3/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 3/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 3/25/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 3/27/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 3/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |