16627 W KNAPP ST 91343

Certificate Information: 16627 W KNAPP ST 91343

Application / Permit
21014-20000-02839
Plan Check / Job No.
B21VN07077
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 21' X 21' DETACHED GARAGE AND ADD 8' X 14' IRR. SHAPE, 13' X 13'-2" IRR. SHAPE AND 14' X 16' TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/29/2021
Issuing Office
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/11/2021 RAPHAEL ROSAS
Corrections Issued 6/13/2021 RAPHAEL ROSAS
Plan Check Approved 12/13/2021 RAPHAEL ROSAS
Building Plans Picked Up 12/27/2021 APPLICANT
Issued 12/29/2021 APPLICANT
CofO in Progress 6/25/2024 RAUL OLAGI
Permit Finaled 7/10/2024 RUBEN SALAS
CofO Issued 7/10/2024 RUBEN SALAS
Permit Finaled 7/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/14/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/19/2021 CARLOS AGUILERA
Sewer availability Cleared 8/19/2021 CARLOS AGUILERA
Construction near power lines Cleared 9/29/2021 JOHN BACON
Grading Pre-Inspection Cleared 10/25/2021 ALEXANDER ANDREWS
Low Impact Development Cleared 11/16/2021 TA ANH
Roof/Waste drainage to street Cleared 12/1/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Hagopyan,, Edmond; Lic. No.: C80143 7939 WENTWORTH STREET      SUNLAND, CA 91040

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/1/2022 Partial Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 4/7/2022 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 4/13/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 9/12/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 10/3/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 12/22/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Approved RAUL OLAGI
Green Building Rough 1/25/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 1/25/2023 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 2/6/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/15/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 2/15/2023 Approved RAUL OLAGI
Green Building Rough 2/15/2023 Approved RAUL OLAGI
HVAC-Rough 2/15/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 2/15/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 2/15/2023 Approved RAUL OLAGI
Insulation 3/3/2023 Approved RAUL OLAGI
Drywall Nailing 3/8/2023 Not Ready for Inspection RAUL OLAGI
Drywall Nailing 3/10/2023 Approved RAUL OLAGI
Shower Pan 4/10/2023 Approved DAVID ANDERSON
ELECTRICAL-Final 10/11/2023 Corrections Issued RAUL OLAGI
Final 10/11/2023 Corrections Issued RAUL OLAGI
HVAC-Final 10/11/2023 Corrections Issued RAUL OLAGI
PLUMBING-Final 10/11/2023 Corrections Issued RAUL OLAGI
Final 4/15/2024 Corrections Issued RAUL OLAGI
Green Building Final 4/15/2024 Not Ready for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/15/2024 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 4/15/2024 Not Ready for Inspection RAUL OLAGI
Final 6/25/2024 OK to Issue CofO RAUL OLAGI
Green Building Final 6/25/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 6/25/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 6/25/2024 Approved RAUL OLAGI