16240 W ITASCA ST 91343

Certificate Information: 16240 W ITASCA ST 91343

Application / Permit
21014-20000-02822
Plan Check / Job No.
B21VN07032
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO FIRST AND SECOND STORY OF THE EXISTING SINGLE FAMILY DWELLING WHICH INCLUDES (N) REC. ROOM AND LAUNDRY ADDITION TO SIDE OF BUILDING, ADDITION AT FRONT OF GARAGE AND (N) STAIRWAY TO SECOND STORY. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 COLIN LOREDO
Corrections Issued 7/15/2021 COLIN LOREDO
Quality Review Completed 7/28/2021 OMID HEDAYAT
Building Plans Picked Up 8/26/2021 APPLICANT
Applicant returned to address corrections 1/18/2022 COLIN LOREDO
Applicant returned to address corrections 3/1/2022 COLIN LOREDO
Plan Check Approved 4/11/2022 COLIN LOREDO
Issued 4/25/2022 APPLICANT
CofO in Progress 1/13/2025 RAUL OLAGI
Permit Finaled 1/17/2025 RUBEN SALAS
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/2/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/2/2021 CARLOS AGUILERA
Sewer availability Cleared 11/2/2021 CARLOS AGUILERA
Low Impact Development Cleared 12/16/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 12/16/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 12/27/2021 TIMOTHY POWELL
GPI Written Notices Cleared 1/18/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/6/2022 Corrections Issued RAUL OLAGI
Special/Order Compliance 5/6/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/9/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 5/13/2022 Partial Approval RAUL OLAGI
Sewer 5/13/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 6/16/2022 Corrections Issued ALAN MORELOS
Pre-Inspection 6/16/2022 Partial Inspection DEANDRE HOFFMAN
Special/Order Compliance 6/16/2022 Partial Inspection WILLIAM WREN
Footing/Foundation/Slab 6/21/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 6/30/2022 Corrections Issued ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Corrections Issued ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Partial Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 8/15/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 8/15/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 8/15/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 8/15/2022 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 8/15/2022 Partial Approval RAUL OLAGI
Insulation 8/22/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 9/12/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 9/12/2022 Approved RAUL OLAGI
Green Building Rough 9/12/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 9/12/2022 Approved RAUL OLAGI
PLUMBING-Rough 9/12/2022 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 9/21/2022 Approved ALAN MORELOS
Green Building Rough 9/21/2022 Approved ALAN MORELOS
Insulation 9/21/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 9/21/2022 Partial Approval ALAN MORELOS
PLUMBING-Rough 9/21/2022 Approved ALAN MORELOS
Wood Frame 9/21/2022 Approved ALAN MORELOS
Shower Pan 9/29/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 9/30/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 9/30/2022 Approved ALAN MORELOS
Final 5/5/2023 Corrections Issued RAUL OLAGI
Green Building Final 5/5/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 5/5/2023 Approved RAUL OLAGI
Final 9/4/2024 Corrections Issued RAUL OLAGI
Final 1/13/2025 OK to Issue CofO RAUL OLAGI