19135 W DELANO ST 91335
Certificate Information: 19135 W DELANO ST 91335
- Application / Permit
- 21014-20000-02821
- Plan Check / Job No.
- B21VN07022
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 31'-3" X 20'-5" TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/16/2022
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | SELLA BENYAMIN |
| Corrections Issued | 7/12/2021 | SELLA BENYAMIN |
| Quality Review Completed | 7/14/2021 | STEVEN KIM |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Issued | 2/16/2022 | APPLICANT |
| Plan Check Approved | 2/17/2022 | SELLA BENYAMIN |
| CofO in Progress | 11/9/2022 | SEAN HAUPT |
| CofO in Progress | 11/9/2022 | SEAN HAUPT |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
| CofO Issued | 12/20/2022 | MICHAEL SMITH |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/13/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/18/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/2/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 12/1/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 2/3/2022 | JULIAN SUNG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/23/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/9/2022 | Corrections Issued | SEAN HAUPT |
| Underground Mechanical | 3/9/2022 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 3/16/2022 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 3/16/2022 | Not Ready for Inspection | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/23/2022 | Corrections Issued | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/25/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/25/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/14/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 4/14/2022 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 4/14/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 4/14/2022 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 4/14/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 5/2/2022 | Approved | SEAN HAUPT |
| Gas Test | 5/2/2022 | Corrections Issued | SEAN HAUPT |
| HVAC-Rough | 5/2/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 5/2/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/18/2022 | Not Ready for Inspection | SEAN HAUPT |
| Insulation | 5/31/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/31/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 7/18/2022 | Partial Inspection | MORRIS JACKSON |
| Underground Mechanical | 7/28/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | SEAN HAUPT |
| Final | 9/29/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 9/29/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 9/29/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/29/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 9/29/2022 | Approved | SEAN HAUPT |
| Final | 11/1/2022 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 11/1/2022 | Not Ready for Inspection | JEFFREY BULL |
| Final | 11/7/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 11/7/2022 | Approved | SEAN HAUPT |