5301 N MELVIN AVE 91356

Certificate Information: 5301 N MELVIN AVE 91356

Application / Permit
21014-20000-02788
Plan Check / Job No.
B21VN06927
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR 9'-4" X 17'-8" TO EXTEND (E) ENTRY AND NEW LAUNDRY ROOM, CONVERT (E) DEN TO (N) BEDROOM, REMODEL THROUGHOUT (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/11/2021 JENNIFER LEE
Corrections Issued 6/15/2021 JENNIFER LEE
Plan Check Approved 9/16/2021 JENNIFER LEE
Building Plans Picked Up 9/17/2021 APPLICANT
Issued 9/23/2021 APPLICANT
CofO in Progress 2/14/2023 DAVID SANDOVAL
Permit Finaled 3/22/2023 JOHN JANSON
CofO Issued 3/22/2023 JOHN JANSON
Permit Finaled 3/22/2023 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/22/2021 BRIAN MILLER
Roof/Waste drainage to street Cleared 8/5/2021 GABRIEL ROBLES
Sewer availability Cleared 8/10/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/13/2021 GABRIEL ROBLES

Contact Information

Contractor Mega Commercial Construction Inc; Lic. No.: 605792-B 7912 BELLAIRE AVE      NORTH HOLLYWOOD, CA 91605
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 2/9/2022 Approved DAVID SANDOVAL
HVAC-Rough 2/9/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 2/9/2022 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 2/16/2022 Approved DAVID SANDOVAL
Green Building Rough 2/16/2022 Approved DAVID SANDOVAL
HVAC-Rough 2/16/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 2/16/2022 Approved DAVID SANDOVAL
Insulation 2/24/2022 Approved PETER FOLLING
Drywall Nailing 3/9/2022 Approved MORRIS JACKSON
Shower Pan 3/9/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/23/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 2/1/2023 Approved SEAN HAUPT
Final 2/1/2023 Corrections Issued SEAN HAUPT
Green Building Final 2/1/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Final 2/1/2023 Approved SEAN HAUPT
PLUMBING-Final 2/1/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 2/1/2023 Approved SEAN HAUPT
ELECTRICAL-Final 2/6/2023 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 2/6/2023 Approved DAVID SANDOVAL
PLUMBING-Final 2/6/2023 Approved DAVID SANDOVAL
ELECTRICAL-Final 2/9/2023 Approved DAVID SANDOVAL
Final 2/9/2023 OK to Issue CofO DAVID SANDOVAL
Green Building Final 2/9/2023 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved DAVID SANDOVAL