7253 W HILLROSE ST 91042

Certificate Information: 7253 W HILLROSE ST 91042

Application / Permit
21014-20000-02774
Plan Check / Job No.
B21VN06898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION IRREGULAR (62'-4" X 20' ) TO (E) SFD FOR NEW BEDROOM, DEN AND ENTRY FOYER. CONVERT ATTACHED GARAGE TO NEW BEDROOM. NEW 7'-10" X 4'-9" ATTACHED ENTRY PATIO COVER. WORK PER ENGINEER. AUTOMATIC FIRE SPRINKLER SYSTEM REQUIRED.
Permit Issued
Issued on 7/25/2022
Issuing Office
Current Status
CofO Issued on 6/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/9/2021 ROSENDO MEDINA
Corrections Issued 6/12/2021 ROSENDO MEDINA
Applicant returned to address corrections 5/20/2022 ROSENDO MEDINA
Plan Check Approved 5/25/2022 ROSENDO MEDINA
Building Plans Picked Up 5/26/2022 APPLICANT
Issued 7/25/2022 APPLICANT
CofO in Progress 6/20/2024 WILLIAM WREN
Permit Finaled 6/26/2024 RUBEN SALAS
CofO Issued 6/26/2024 RUBEN SALAS
Permit Finaled 6/26/2024 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 1/20/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/2/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/3/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 3/11/2022 LARRY REDDEN
Grading Pre-Inspection Cleared 3/16/2022 VASIL MIHALEV
GPI Written Notices Cleared 5/24/2022 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/27/2022 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 4/18/2023 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 4/19/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 4/19/2023 Partial Approval WILLIAM WREN
Deputy Drilled-In Anchors 6/6/2023 Conditional Approval WILLIAM WREN
Footing/Foundation/Slab 6/8/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 11/30/2023 Approved ROY SPAULDING
HVAC-Rough 11/30/2023 Corrections Issued ROY SPAULDING
PLUMBING-Rough 11/30/2023 Approved ROY SPAULDING
Deputy Wood Construction 12/1/2023 Conditional Approval JUAN VALENZUELA
Green Building Rough 12/5/2023 Approved WILLIAM WREN
HVAC-Rough 12/5/2023 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 12/7/2023 Approved WILLIAM WREN
FLOOD-Proofing Certificate 12/7/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/7/2023 Approved WILLIAM WREN
Insulation 12/13/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 12/13/2023 Approved WILLIAM WREN
Drywall Nailing 12/20/2023 Approved WILLIAM WREN
Shower Pan 12/20/2023 Approved WILLIAM WREN
Final 5/23/2024 Corrections Issued WILLIAM WREN
Green Building Final 5/23/2024 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 5/23/2024 SGSOV Approved WILLIAM WREN
Smoke Detectors 5/23/2024 Approved WILLIAM WREN
Final 5/30/2024 OK to Issue CofO WILLIAM WREN