19539 W BERMUDA ST 91326

Certificate Information: 19539 W BERMUDA ST 91326

Application / Permit
21014-20000-02769
Plan Check / Job No.
B21VN06893
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 21'-1" X 25' IRREGULAR SHAPED ADDITION AT REAR AND 3'-2" X 9-2"' ADDITION AT FRONT AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/28/2021
Issuing Office
Current Status
CofO Issued on 7/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2021 APPLICANT
Assigned to Plan Check Engineer 6/4/2021 RAPHAEL ROSAS
Corrections Issued 6/4/2021 RAPHAEL ROSAS
Applicant returned to address corrections 8/17/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/6/2021 RAPHAEL ROSAS
Plan Check Approved 12/16/2021 RAPHAEL ROSAS
Building Plans Picked Up 12/17/2021 APPLICANT
Issued 12/28/2021 APPLICANT
CofO in Progress 8/16/2023 DAVID SCANTLIN
CofO in Progress 11/2/2023 JOHN KIDWELL
Permit Finaled 7/10/2024 JOHN JANSON
CofO Issued 7/10/2024 JOHN JANSON
Permit Finaled 7/10/2024 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 6/9/2021 ANNA VIDAL
Roof/Waste drainage to street Cleared 7/8/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/13/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 8/16/2021 RAPHAEL ROSAS
Low Impact Development Cleared 11/18/2021 MARCO SANCHEZ
GPI Written Notices Cleared 12/6/2021 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/7/2022 Corrections Issued HENRY KIM
Footing/Foundation/Slab 1/18/2022 Partial Approval HENRY KIM
PLUMBING-Rough 1/18/2022 Partial Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 2/4/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 2/4/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 5/12/2022 Corrections Issued JEFFREY PARD
ELECTRICAL-Rough 5/12/2022 Approved JEFFREY PARD
Green Building Rough 5/12/2022 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 5/12/2022 Corrections Issued JEFFREY PARD
PLUMBING-Rough 5/12/2022 Approved JEFFREY PARD
Wood Frame 5/25/2022 Approved JEFFREY PARD
Insulation 6/3/2022 Approved KRISTEN CAUSEY
Drywall Nailing 8/4/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 8/4/2022 Partial Approval KRISTEN CAUSEY
Shower Pan 8/4/2022 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 4/17/2023 Approved DAVID SCANTLIN
ELECTRICAL-Final 4/17/2023 Approved DAVID SCANTLIN
Final 4/17/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 4/17/2023 Approved DAVID SCANTLIN
Green Building Rough 4/17/2023 Approved DAVID SCANTLIN
HVAC-Final 4/17/2023 Approved DAVID SCANTLIN
PLUMBING-Final 4/17/2023 Approved DAVID SCANTLIN
Smoke Detectors 4/17/2023 Approved DAVID SCANTLIN
Special/Order Compliance 4/17/2023 Partial Inspection MORRIS JACKSON
Final 8/16/2023 OK to Issue CofO DAVID SCANTLIN
Special/Order Compliance 8/16/2023 Partial Inspection JEFFREY HARTLINE
Final 11/1/2023 OK to Issue CofO JOHN KIDWELL
Special/Order Compliance 4/24/2024 Approved DAVID SCANTLIN