2308 N HILLHURST AVE 90027

Certificate Information: 2308 N HILLHURST AVE 90027

Application / Permit
21014-20000-02768
Plan Check / Job No.
B21VN06891
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 11'-9" X 8'-9" ENTRY PORCH & 16'-2" X 4'-8" DINING ROOM AND REMODEL TO (E) ONE-STORY S.F.D AND RE-FRAME (E) STUDY AND CONVERT TO FAMILY ROOM' WORK PER ENGINEER.
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 5/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 TROY DEGUZMAN
Corrections Issued 7/9/2021 TROY DEGUZMAN
Quality Review Completed 7/15/2021 OMID HEDAYAT
Building Plans Picked Up 7/16/2021 APPLICANT
Plan Check Approved 10/20/2021 TROY DEGUZMAN
Issued 10/20/2021 APPLICANT
CofO in Progress 5/6/2024 JOSEPH MCGARRY
CofO Issued 5/16/2024 DEROLD HAUFF
Permit Finaled 5/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/19/2021 WALLIE JONG
Sewer availability Cleared 7/19/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/20/2021 WALLIE JONG
GPI Written Notices Cleared 10/20/2021 TROY DEGUZMAN
Grading Pre-Inspection Cleared 10/20/2021 TROY DEGUZMAN
Green Code Cleared 10/20/2021 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2022 Partial Approval JOSEPH MCGARRY
Wood Frame 5/23/2022 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/24/2022 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 5/27/2022 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 5/27/2022 Conditional Approval JOSEPH MCGARRY
Wood Frame 6/8/2022 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 6/24/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 6/24/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/8/2022 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 8/30/2022 Approved JOSEPH MCGARRY
Green Building Rough 8/30/2022 Approved JOSEPH MCGARRY
Insulation 8/30/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 8/30/2022 Approved JOSEPH MCGARRY
Drywall Nailing 9/8/2022 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 3/6/2023 Approved JEFFREY MEAD
HVAC-Rough 3/6/2023 Approved JEFFREY MEAD
Wood Frame 3/6/2023 Approved JEFFREY MEAD
Insulation 3/14/2023 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 3/14/2023 Approved CHARLES BOGHOSKHAN
Drywall Nailing 3/21/2023 Approved JOSEPH MCGARRY
Final 4/7/2023 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 4/7/2023 Approved JOSEPH MCGARRY
Green Building Final 4/7/2023 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 4/7/2023 Approved JOSEPH MCGARRY
Final 4/26/2024 Not Ready for Inspection JOSEPH MCGARRY
Final 4/30/2024 OK to Issue CofO JOSEPH MCGARRY