4856-4858 N HEAVEN AVE 91364
Certificate Information: 4856-4858 N HEAVEN AVE 91364
- Application / Permit
- 21014-20000-02767
- Plan Check / Job No.
- B21VN06887
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 23'-10" x 21'-0" ADDITION OF A (N) ACCESSORY DWELLING UNIT TO THE (E) SINGLE FAMILY DWELLING PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- CofO Issued on 8/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 6/12/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 5/31/2022 | SARKIS HARABEDIAN |
| Issued | 5/31/2022 | APPLICANT |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| CofO in Progress | 8/7/2023 | JOHN KIDWELL |
| Permit Finaled | 8/16/2023 | DANIEL ORRANTE |
| CofO Issued | 8/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/27/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | ABDULLAH SADOZAI |
| Grading Pre-Inspection | Cleared | 5/24/2022 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Redwood Constructors Inc; Lic. No.: 1073761-B | 5714 RAINBOW HILL RD AGOURA HILLS, CA 91301 |
| Engineer | Andrejic,, Milos M; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/8/2022 | Conditional Approval | MICHAEL SMITH |
| PLUMBING-Rough | 7/8/2022 | Partial Approval | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Approved | PETER FOLLING |
| Deputy Reinf. Concrete | 7/13/2022 | No Access for Inspection | PETER FOLLING |
| Deputy Drilled-In Anchors | 9/1/2022 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/12/2022 | No Access for Inspection | PETER FOLLING |
| Green Building Rough | 9/12/2022 | No Access for Inspection | PETER FOLLING |
| MERV13>=Rough | 9/12/2022 | No Access for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Approved | VINCENT HANLEY |
| Sewer | 9/16/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 10/28/2022 | Approved | PETER FOLLING |
| HVAC-Rough | 10/28/2022 | Approved | PETER FOLLING |
| Insulation | 10/28/2022 | Approved | PETER FOLLING |
| PLUMBING-Rough | 10/28/2022 | Approved | PETER FOLLING |
| Drywall Nailing | 11/9/2022 | Approved | PETER FOLLING |
| Green Building Rough | 11/9/2022 | Approved | PETER FOLLING |
| Shower Pan | 11/9/2022 | Approved | PETER FOLLING |
| Shower Pan | 11/14/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/12/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 6/12/2023 | Approved | PETER FOLLING |
| Final | 6/12/2023 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 6/12/2023 | Approved | PETER FOLLING |
| Green Building Final | 6/12/2023 | Approved | PETER FOLLING |
| HVAC-Final | 6/12/2023 | Not Ready for Inspection | PETER FOLLING |
| MERV13>=Final | 6/12/2023 | Approved | PETER FOLLING |
| MERV13>=Rough | 6/12/2023 | Approved | PETER FOLLING |
| PLUMBING-Final | 6/12/2023 | Approved | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Not Ready | PETER FOLLING |
| Smoke Detectors | 6/12/2023 | Approved | PETER FOLLING |
| Final | 8/4/2023 | OK to Issue CofO | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | JOHN KIDWELL |