2251 N HIDALGO AVE 90039

Certificate Information: 2251 N HIDALGO AVE 90039

Application / Permit
21014-20000-02765
Plan Check / Job No.
B21VN06883
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (30'-6"x17'-0") OF 2 STORY DECK TO EXISTING SINGLE FAMILY DWELLING, (124 SQFT IS COVERED)
Permit Issued
Issued on 5/11/2023
Issuing Office
Current Status
Issued on 5/11/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 PETER MOSESIAN
Corrections Issued 7/24/2021 PETER MOSESIAN
Quality Review Completed 8/17/2021 OMID HEDAYAT
Building Plans Picked Up 8/19/2021 APPLICANT
Applicant returned to address corrections 10/15/2021 PETER MOSESIAN
Plan Check Approved 10/25/2022 PETER MOSESIAN
Issued 5/11/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/9/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/15/2021 JEANIE LAM

Contact Information

Contractor Omega Structural Inc; Lic. No.: 998075-B 4269 S HARVARD BOULEVARD      LOS ANGELES, CA 90062
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342
Geologist Hoek,, Johan; Lic. No.: EG2544 10369 SILVERSTON AVE      TUJUNGA, CA 91042

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 11/16/2023 Approved THOMAS LOGRASSO
Deputy Steel/Welding 1/31/2024 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 5/6/2024 Approved HAMIK HARTOUNIAN
Structural Steel Frame 10/17/2024 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 10/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 1/15/2025 Corrections Issued HAMIK HARTOUNIAN
Structural Steel Frame 2/19/2025 Approved HAMIK HARTOUNIAN
Final 2/27/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/27/2025 Approved HAMIK HARTOUNIAN
Green Building Final 2/27/2025 Approved HAMIK HARTOUNIAN
Green Building Rough 2/27/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/27/2025 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 2/27/2025 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 2/27/2025 Approved HAMIK HARTOUNIAN
Final 4/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 4/24/2025 Approved ALIZAH MAYAGOITIA