16754 W HUERTA ROAD 91436
Certificate Information: 16754 W HUERTA ROAD 91436
- Application / Permit
- 21014-20000-02754
- Plan Check / Job No.
- B21VN06861
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1539 SQFT ADDITION AND REMODELING TO AN EXISTING 2 STORY RESIDENCE. 1234 SQ.FT ADDITION TO 1ST FLOOR, 305 SQ.FT. ADDITION TO 2ND FLOOR.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- Issued on 12/3/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | PETER MOSESIAN |
| Corrections Issued | 7/9/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/15/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/19/2021 | APPLICANT |
| Plan Check Approved | 12/3/2021 | JON BLAINE |
| Issued | 12/3/2021 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/3/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/3/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/3/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/3/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 8/3/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/3/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 9/21/2021 | ALEXANDER ANDREWS |
| Low Impact Development | Cleared | 10/20/2021 | SAHIL SHARMA |
| Roof/Waste drainage to street | Cleared | 10/20/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 2/22/2022 | Partial Inspection | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/14/2022 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/21/2022 | Partial Approval | PETER FOLLING |
| Footing/Foundation/Slab | 5/11/2022 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 6/6/2022 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 6/9/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 2/3/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/6/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/3/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/11/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/11/2024 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/24/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 6/24/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/17/2024 | Approved | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/5/2024 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Partial Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/5/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 9/11/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/16/2024 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 9/16/2024 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 9/16/2024 | Approved | JOHN KIDWELL |
| Insulation | 10/29/2024 | Approved | THOMAS FINNILA |
| Wood Frame | 10/29/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/8/2024 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 2/26/2025 | Approved | SCOTT SOBEL |
| Shower Pan | 2/26/2025 | Partial Approval | SCOTT SOBEL |
| Shower Pan | 3/4/2025 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/9/2026 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 2/9/2026 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 2/23/2026 | Approved | SEAN WIRCH |
| PLUMBING-Final | 2/23/2026 | Approved | SEAN WIRCH |