6623 W 82ND ST 90045
Certificate Information: 6623 W 82ND ST 90045
- Application / Permit
- 21014-20000-02742
- Plan Check / Job No.
- B21VN06824
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL; REMOVE SINGLE FAMILY DWELLING EXCEPT FOR 2'-4" LINEAR FEET OF FOOTING ON SOUTH SIDE OF LOT; ADD 39'-1" X 52'-6" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 2/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | SELLA BENYAMIN |
| Corrections Issued | 6/22/2021 | SELLA BENYAMIN |
| Quality Review Completed | 6/24/2021 | STEVEN KIM |
| Building Plans Picked Up | 6/28/2021 | APPLICANT |
| Plan Check Approved | 12/10/2021 | SELLA BENYAMIN |
| Issued | 2/25/2022 | APPLICANT |
| CofO in Progress | 7/7/2023 | BOBBY KEY |
| Permit Finaled | 7/10/2023 | DANIEL ORRANTE |
| CofO Issued | 7/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 7/14/2021 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/26/2021 | HISASHI KOBAYAKAWA |
| Trees in Parkway | Cleared | 8/12/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 9/4/2021 | RUEL COLE |
| Low Impact Development | Cleared | 11/18/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 7919 SAUSALITO AVE WEST HILLS, CA 91304 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/18/2022 | Partial Inspection | BOBBY KEY |
| PLUMBING-Rough | 5/9/2022 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 5/26/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/6/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Corrections Issued | HERBERT GIRON |
| Structural Steel Frame | 7/28/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | BOBBY KEY |
| Structural Steel Frame | 8/1/2022 | Approved | BOBBY KEY |
| Deputy Wood Construction | 9/30/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 11/1/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/15/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 12/15/2022 | Approved | BOBBY KEY |
| Gas Test | 12/15/2022 | Partial Approval | BOBBY KEY |
| Green Building Rough | 12/15/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 12/15/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/15/2022 | Approved | BOBBY KEY |
| Final | 1/6/2023 | Corrections Issued | BOBBY KEY |
| Insulation | 1/6/2023 | Approved | BOBBY KEY |
| Underground Mechanical | 1/6/2023 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 1/10/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 1/17/2023 | Approved | BOBBY KEY |
| Final | 1/17/2023 | Corrections Issued | BOBBY KEY |
| Shower Pan | 1/26/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/8/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 5/25/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 5/25/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 6/12/2023 | Approved | BOBBY KEY |
| HVAC-Final | 6/12/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/12/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 7/6/2023 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 7/6/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/6/2023 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 7/6/2023 | Approved | BOBBY KEY |
| Final | 7/7/2023 | OK to Issue CofO | BOBBY KEY |
| PLUMBING-Final | 7/7/2023 | Approved | BOBBY KEY |
| Service/Power Release | 7/7/2023 | Approved | BOBBY KEY |