13260 1/2 N GLADSTONE AVE 91342
Certificate Information: 13260 1/2 N GLADSTONE AVE 91342
- Application / Permit
- 21014-20000-02737
- Plan Check / Job No.
- B21VN06818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 7'-5" X 16'-7" ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 6/5/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/27/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 12/29/2021 | APPLICANT |
| Issued | 3/18/2022 | APPLICANT |
| CofO in Progress | 3/8/2023 | ARAM AVEDISIAN |
| CofO Issued | 4/26/2023 | MICHAEL SMITH |
| Permit Finaled | 4/26/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/19/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/4/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 121 N VAIL AVE MONTEBELLO, CA 90640 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/24/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 3/24/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/11/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 5/19/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 7/21/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/21/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 7/21/2022 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 7/22/2022 | No Result Entered | KENNETH KUROWSKI |
| HVAC-Rough | 8/11/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 8/11/2022 | Partial Approval | DEANDRE HOFFMAN |
| Gas Test | 8/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 8/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 8/15/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/18/2022 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 8/18/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 8/23/2022 | Conditional Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 8/23/2022 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 8/23/2022 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 9/1/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 9/1/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/1/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/29/2022 | Approved | ARAM AVEDISIAN |
| Final | 12/29/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 12/29/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/29/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 12/29/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 12/29/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/8/2023 | Approved | ARAM AVEDISIAN |
| Final | 3/8/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 3/8/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 3/8/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 3/8/2023 | SGSOV Approved | ARAM AVEDISIAN |