16312 W MINNEHAHA ST 91344

Certificate Information: 16312 W MINNEHAHA ST 91344

Application / Permit
21014-20000-02732
Plan Check / Job No.
B21VN06797
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 11'-3" X 16'-4" IRREGULAR SHAPE PORCH AND ADD 7'-11" X 25'-11" AND REMODEL (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/19/2021
Issuing Office
Current Status
Issued on 6/19/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/1/2021 APPLICANT
Assigned to Plan Check Engineer 6/2/2021 RAPHAEL ROSAS
Corrections Issued 6/3/2021 RAPHAEL ROSAS
Issued 6/19/2021 APPLICANT
Building Plans Picked Up 6/22/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/8/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/8/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/8/2021 DAGOVERTO GUERRERO

Contact Information

Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/23/2021 Approved MARK JOHNSON
Deputy Drilled-In Anchors 6/29/2021 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 6/29/2021 Conditional Approval MARK JOHNSON
Footing/Foundation/Slab 6/29/2021 Conditional Approval MARK JOHNSON
Excavation/Setback/Form/Re-Bar 7/2/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 7/20/2021 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 7/20/2021 Corrections Issued MICHAEL PELHAM
HVAC-Rough 7/20/2021 Corrections Issued MICHAEL PELHAM
PLUMBING-Rough 7/20/2021 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 7/22/2021 Partial Approval MARK JOHNSON
HVAC-Rough 7/22/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 7/22/2021 Partial Approval MARK JOHNSON
Wood Frame 7/22/2021 Partial Approval MARK JOHNSON
Deputy Wood Construction 7/23/2021 Conditional Approval DANIEL ORRANTE
Deputy Wood Construction 7/26/2021 Conditional Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Approved MARK JOHNSON
HVAC-Rough 7/27/2021 Partial Approval MARK JOHNSON
Wood Frame 7/27/2021 Partial Approval MARK JOHNSON
Insulation 8/2/2021 Approved WILLIAM WREN
Drywall Nailing 8/12/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 8/12/2021 Approved MARK JOHNSON
Drywall Nailing 8/19/2021 Approved ADAM ESCOTO
Drywall Nailing 9/27/2021 Partial Inspection ADAM ESCOTO
Interior/Exterior Lathing 9/27/2021 Not Ready for Inspection ADAM ESCOTO
Interior/Exterior Lathing 9/29/2021 Partial Approval ADAM ESCOTO
BUILDING-Rough-Frame 1/26/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 1/26/2022 Corrections Issued JENNIFER RABUCHIN
Final 1/26/2022 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 1/26/2022 Approved JENNIFER RABUCHIN
Green Building Final 1/26/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/26/2022 Approved JENNIFER RABUCHIN
HVAC-Final 1/26/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 1/26/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/26/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/5/2022 Partial Approval JAVIER RAMOS JR
Final 8/5/2022 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 8/5/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 8/5/2022 Partial Approval JAVIER RAMOS JR
PLUMBING-Final 8/5/2022 Approved JAVIER RAMOS JR