10503 W WOODBRIDGE ST 91602
Certificate Information: 10503 W WOODBRIDGE ST 91602
- Application / Permit
- 21014-20000-02728
- Plan Check / Job No.
- B21VN06776
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 177 SQ. FT. ADDITION TO EXPAND AND REMODEL THE (E) KITCHEN.
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/9/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/18/2021 | MOHAMMAD ESMAILI |
| Issued | 7/19/2021 | APPLICANT |
| CofO in Progress | 7/29/2022 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/29/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Woodcraft,, Astra E; Lic. No.: C32722 | 20812 VENTURA BLVD SUITE 205 WOODLAND HILLS, CA 91364 |
| Contractor | Ucal Services Inc; Lic. No.: 744809-B | 5631 GRAVES AVENUE ENCINO, CA 91316 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/25/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/26/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/30/2021 | Conditional Approval | THOMAS FINNILA |
| Wood Frame | 9/7/2021 | Partial Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 10/14/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/18/2021 | Partial Inspection | THOMAS FINNILA |
| HVAC-Rough | 10/18/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 10/18/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/25/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 10/25/2021 | Approved | CALEB MEISTER |
| Insulation | 11/1/2021 | Conditional Approval | CALEB MEISTER |
| Drywall Nailing | 11/8/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 12/22/2021 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 12/22/2021 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 12/27/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 12/27/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 3/14/2022 | Corrections Issued | MATT KELLERMAN |
| Final | 3/14/2022 | Corrections Issued | MATT KELLERMAN |
| Footing/Foundation/Slab | 3/14/2022 | Approved | MATT KELLERMAN |
| Green Building Final | 3/14/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Final | 3/14/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 3/14/2022 | Approved | MATT KELLERMAN |
| ELECTRICAL-Final | 4/4/2022 | Approved | THOMAS FINNILA |
| Final | 5/18/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 7/14/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 7/28/2022 | OK to Issue CofO | THOMAS FINNILA |