15227 W HARTSOOK ST 91403

Certificate Information: 15227 W HARTSOOK ST 91403

Application / Permit
21014-20000-02722
Plan Check / Job No.
B21VN06765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND 43'-0" FT. X 40'-0" FT, 1460 SQ. FT. IRREGULAR SHAPE ADDITION TO THE (E) SINGLE FAMILY DWELLING AND CONVERT (E) ATTACHED 1-CAR GARAGE TO 2-CAR GARAGE. NFPA 13D FIRE SPRINLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/8/2021 COLIN LOREDO
Corrections Issued 7/13/2021 COLIN LOREDO
Quality Review Completed 7/19/2021 OMID HEDAYAT
Building Plans Picked Up 7/21/2021 APPLICANT
Applicant returned to address corrections 9/1/2021 COLIN LOREDO
Plan Check Approved 9/16/2021 COLIN LOREDO
No Progress 9/16/2021 COLIN LOREDO
Plan Check Approved 9/16/2021 COLIN LOREDO
Plan Check Approved 12/30/2021 COLIN LOREDO
Issued 12/30/2021 APPLICANT
CofO in Progress 2/9/2023 THOMAS FINNILA
Permit Finaled 3/7/2023 MICHAEL SMITH
CofO Issued 3/7/2023 MICHAEL SMITH
Permit Finaled 3/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/13/2021 GABRIEL ROBLES
Sewer availability Cleared 8/13/2021 GABRIEL ROBLES
ZI Cleared 8/17/2021 PABLO ESTRADA
Low Impact Development Cleared 12/9/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 12/13/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Jason K; Lic. No.: S6095 1529 W LONGHILL DR      MONTEREY PARK, CA 91754

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2022 Approved JACK KARGODORIAN
Underground Mechanical 3/30/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/12/2022 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/20/2022 Approved JACK KARGODORIAN
Footing/Foundation/Slab 5/4/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/23/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 6/23/2022 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 6/23/2022 Not Ready for Inspection JACK KARGODORIAN
Underground Mechanical 7/18/2022 Corrections Issued MATT KELLERMAN
ELECTRICAL-Rough 7/20/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 7/20/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 7/20/2022 Corrections Issued MISAEL ESPARZA
Wood Frame 7/20/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 7/27/2022 Corrections Issued JACK KARGODORIAN
HVAC-Rough 7/27/2022 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 7/27/2022 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 8/5/2022 Approved JACK KARGODORIAN
Gas Test 8/5/2022 Approved JACK KARGODORIAN
HVAC-Rough 8/5/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 8/5/2022 Approved JACK KARGODORIAN
Insulation 8/11/2022 Corrections Issued JACK KARGODORIAN
Wood Frame 8/11/2022 Approved JACK KARGODORIAN
Insulation 8/16/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 8/16/2022 Approved CALEB MEISTER
Drywall Nailing 8/29/2022 Approved ASHLEY THOMPSON
Green Building Rough 8/29/2022 Approved ASHLEY THOMPSON
Shower Pan 8/29/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 9/6/2022 Partial Approval JACK KARGODORIAN
ELECTRICAL-Final 1/18/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 1/18/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 1/26/2023 Corrections Issued THOMAS FINNILA
HVAC-Final 1/26/2023 Approved THOMAS FINNILA
PLUMBING-Final 1/26/2023 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 2/7/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 2/7/2023 Corrections Issued THOMAS FINNILA
Green Building Final 2/7/2023 Approved THOMAS FINNILA
PLUMBING-Final 2/7/2023 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Approved THOMAS FINNILA
Smoke Detectors 2/7/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 2/9/2023 Approved THOMAS FINNILA
Final 2/9/2023 OK to Issue CofO THOMAS FINNILA