15227 W HARTSOOK ST 91403
Certificate Information: 15227 W HARTSOOK ST 91403
- Application / Permit
- 21014-20000-02722
- Plan Check / Job No.
- B21VN06765
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND 43'-0" FT. X 40'-0" FT, 1460 SQ. FT. IRREGULAR SHAPE ADDITION TO THE (E) SINGLE FAMILY DWELLING AND CONVERT (E) ATTACHED 1-CAR GARAGE TO 2-CAR GARAGE. NFPA 13D FIRE SPRINLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/30/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | COLIN LOREDO |
| Corrections Issued | 7/13/2021 | COLIN LOREDO |
| Quality Review Completed | 7/19/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/21/2021 | APPLICANT |
| Applicant returned to address corrections | 9/1/2021 | COLIN LOREDO |
| Plan Check Approved | 9/16/2021 | COLIN LOREDO |
| No Progress | 9/16/2021 | COLIN LOREDO |
| Plan Check Approved | 9/16/2021 | COLIN LOREDO |
| Plan Check Approved | 12/30/2021 | COLIN LOREDO |
| Issued | 12/30/2021 | APPLICANT |
| CofO in Progress | 2/9/2023 | THOMAS FINNILA |
| Permit Finaled | 3/7/2023 | MICHAEL SMITH |
| CofO Issued | 3/7/2023 | MICHAEL SMITH |
| Permit Finaled | 3/7/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/13/2021 | GABRIEL ROBLES |
| ZI | Cleared | 8/17/2021 | PABLO ESTRADA |
| Low Impact Development | Cleared | 12/9/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/13/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 1529 W LONGHILL DR MONTEREY PARK, CA 91754 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/8/2022 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 3/30/2022 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 4/20/2022 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 5/4/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 6/23/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 7/18/2022 | Corrections Issued | MATT KELLERMAN |
| ELECTRICAL-Rough | 7/20/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 7/20/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/20/2022 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 7/20/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/27/2022 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 7/27/2022 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 7/27/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 8/5/2022 | Approved | JACK KARGODORIAN |
| Gas Test | 8/5/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 8/5/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/5/2022 | Approved | JACK KARGODORIAN |
| Insulation | 8/11/2022 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 8/11/2022 | Approved | JACK KARGODORIAN |
| Insulation | 8/16/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/16/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 8/29/2022 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 8/29/2022 | Approved | ASHLEY THOMPSON |
| Shower Pan | 8/29/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 1/18/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 1/18/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 1/26/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 1/26/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 1/26/2023 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/7/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/7/2023 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 2/7/2023 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 2/7/2023 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 2/7/2023 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 2/9/2023 | Approved | THOMAS FINNILA |
| Final | 2/9/2023 | OK to Issue CofO | THOMAS FINNILA |