6011 S KANSAS AVE 90044
Certificate Information: 6011 S KANSAS AVE 90044
- Application / Permit
- 21014-20000-02712
- Plan Check / Job No.
- B21VN06745
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GROUND FLOOR ADDITION TO DETACHED GARAGE AND CONVERT TO ADU.
- Permit Issued
- Issued on 8/23/2021
- Issuing Office
- Current Status
- CofO Issued on 9/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2021 | JOE VO |
| Corrections Issued | 6/8/2021 | JOE VO |
| Applicant returned to address corrections | 7/5/2021 | JOE VO |
| Plan Check Approved | 7/13/2021 | JOE VO |
| Issued | 8/23/2021 | APPLICANT |
| CofO in Progress | 9/7/2023 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 9/13/2023 | DEROLD HAUFF |
| CofO Issued | 9/13/2023 | DEROLD HAUFF |
| Permit Finaled | 9/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/29/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2021 | JEANIE LAM |
| Sewer availability | Cleared | 7/8/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/29/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/6/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Pre-Inspection | 5/17/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/31/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/30/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/13/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 7/21/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 8/23/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/6/2022 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/22/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/22/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 3/22/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 3/22/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/22/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 3/22/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 4/5/2023 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Rough | 4/5/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 4/5/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 4/5/2023 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/18/2023 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/18/2023 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 4/18/2023 | Approved | BRENDAN MORELLI |
| Insulation | 5/10/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 5/30/2023 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 7/18/2023 | Corrections Issued | BRENDAN MORELLI |
| Underground Mechanical | 7/21/2023 | Approved | BRENDAN MORELLI |
| Final | 8/10/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 8/10/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/10/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/10/2023 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/21/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/1/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/6/2023 | Approved | ALEJANDRO DE ARTOLA |
| Final | 9/6/2023 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Gas Test | 9/6/2023 | Approved | ALEJANDRO DE ARTOLA |